Forum quick links
Furniture Installation vs. Occupancy
CI-v4 EQc4:Indoor air quality assessmentposted by Michelle Rosenberger on
If the project schedule indicates that move in will occur prior to the completion of furniture installation, can this credit be achieved by flush out?
Flush-out in phases
CI-v4 EQc4:Indoor air quality assessmentposted by Roshni Mathur on
We are working on a project wherein the interior fit-out work will be carried out in 2 phases. Consequtively the occupancy will be in 2 phases aswell.
Air Testing Agency Hiring Requirements
CI-v4 EQc4:Indoor air quality assessmentposted by Amgad Khattab on
Hi All,
I'm working on a commercial interiors project that's pursuing both option.2 Air testing.
IAQ testing - WELL / LEED crosswalks or ACP option?
CI-v4 EQc4:Indoor air quality assessmentposted by Yarden Harari on
Hi All,
IAQ Assessment - Air Testing
CI-v4 EQc4:Indoor air quality assessmentposted by Harvard University Green Building Services on
For one of our LEEDv4 CI projects the project team was looking to conduct Air Testing in order to meet the credit requirements for the Indoor Air Quality Assessment credit.
Multi floor Office Building - Can each floor be flushed as it gets installed?
CI-v4 EQc4:Indoor air quality assessmentposted by Susan Di Giulio on
Dear colleagues,
Calculations needed for the whole project or each space?
CI-v4 EQc4:Indoor air quality assessmentposted by Katarzyna Toczynska on
Hi everyone!
Gross Floor area Question
CI-v4 EQc4:Indoor air quality assessmentposted by Nancy Henderson on
We have a tenant with several full floors being built out in a new core and shell building. Does the gross SF for the purpose of the flush out need to include what would be considered core sp
Does IT and AV equipment need to be installed prior to IAQ testing?
CI-v4 EQc4:Indoor air quality assessmentposted by Diana Smiciklas on
Does IT and AV equipment need to be installed prior to IAQ testing? We are moving offices and our IT team will be dismantling and reinstalling AV and IT equipment the weekend prior to our move.
Expiration of Emission Testing Certificates
CI-v4 EQc4:Indoor air quality assessmentposted by Maria Fiorelli on
Is it acceptable to upload certificates backing up emissions testing (i.e.