Dear colleagues,
We have a multi-floor Office Building. Can each floor be installed with furniture then flushed, starting at the ground level then moving up. This is to accommodate a tight schedule. Each floor has fan rooms.
Thank you for your guidance.
emily reese moody
Sustainability Director, Certifications & ComplianceJacobs
LEEDuser Expert
476 thumbs up
April 12, 2021 - 6:40 pm
Hi Susan,
See if this post from the NC version of this credit is helpful: http://leeduser.buildinggreen.com/forum/iaq-testing-3
(also let me know if this link doesn't work...having a hard time posting links lately)