Can the Projects Fundamental CxA be an employee of the Mechanical Design firm, but not part of MEP Design Team?
NC-v4 EAp1:Fundamental commissioning and verificationposted by marc myers on
- The CxA may be a qualified employee of the owner, an independent consultant, or an employee of the design or construction firm who is not part of the project’s design or construction team, o
How to Perform fundamental commisiioning and verification of VRF System?
NC-v4 EAp1:Fundamental commissioning and verificationposted by JASON NIEN on
we have a VRF(Variable Refrigerant Flow) system for air conditioning . if we want to execute commissioning , how can i do this credit ? how to verify VRF system performance? thanks .
Issues & Benefits Log - seeking clarification
NC-v4 EAp1:Fundamental commissioning and verificationposted by Joyce Kelly on
Trying to figure out how the Benefits side of this Log might work.
Change to Cx agent
NC-v4 EAp1:Fundamental commissioning and verificationposted by Cindy Quinn on
I'm working on a v4 project currently in CD design phase.
Envelope CxA Requirements
NC-v4 EAp1:Fundamental commissioning and verificationposted by Risto Beatty on
Do the rules for who can be a CxA also apply to envelope commissioning? That is, can the envelope consultant on a project also perform the envelope commissioning?
Pending commissioning completion
NC-v4 EAp1:Fundamental commissioning and verificationposted by Charalampos Giannikopoulos on
Projects registered with LEED v3 had an option of indicating that commissioning report is pending completion and providing a contract to ensure that the report will be completed.
Cx plan
NC-v4 EAp1:Fundamental commissioning and verificationposted by Joshua Roy on
Does anyone have an example Cx plan?
LEED v4 CxA
NC-v4 EAp1:Fundamental commissioning and verificationposted by P. Hardy on
In LEED v4, the CxA for Enhanced Commissioning must be independent of the design and construction team- but what if the construction team is also the owner, as in design-build?
District Energy Cx Guidance
NC-v4 EAp1:Fundamental commissioning and verificationposted by Candice Rogers on
Hello, We have a project that meets the requirements of District Energy Systems. There is one new piece of equipment and multiple existing that will serve the facility.
Data Center CxA
NC-v4 EAp1:Fundamental commissioning and verificationposted by Peter Dishno on
The LEED V4 book has the comment: "DATA CENTERS ONLY For small projects with computer room peak cooling loads less than 2,000,000 Btu/h (600 kW) or a total computer room peak cooling load less tha