shop-applied finishes are not covered by LEED

General forums
posted by Tristan Roberts on Mar 25, 2010, 3:17 pm

Good news, Simon. Since the finish you're using is to be "shop-applied," or oiled off-site, it is not subject to the LEED IEQc4.2...

Last reply: Tristan Roberts, Mar 29, 2010, 10:42 am

Must C&S HVAC certified under 62.1-2004 upgrade to 2007 for CI?

CI-2009 IEQp1: Minimum indoor air quality performance
posted by David Posada on Mar 26, 2010, 6:22 am

If a CI project is being built out in a building that is certified under Core and Shell to meet ASHRAE 62.1-2004, does this prerequisite require that all spaces within the scope of the TI meet 62...

Last reply: Roger Chang, Mar 28, 2010, 9:54 am

Calculating the hardscapes that are shaded

EBOM-2009 SSc7.1: Heat island effect - nonroof
posted by RASHID HAMEEN on Mar 25, 2010, 4:05 am

The guide requires that we need to calculate the shaded areas at 10 am, 12 noon and on 3pm on the summer solstice? My question is do we need to calculate on specifically on this day? what if June...

Last reply: Tristan Roberts, Mar 26, 2010, 11:08 am

Industrial Site-Process Water

EBOM-2009 WEp1: Minimum Indoor Plumbing Fixture and Fitting Efficiency
posted by Dianne Herrin on Mar 26, 2010, 4:51 am

Hi -My building is an industrial site. They use substantial potable process water to "waterproof test" assembled product. I am presuming this does not need to be included here or in WEC2? Can...

Last reply: Tristan Roberts, Mar 26, 2010, 11:03 am

SRI compliant paints

EBOM-2009 SSc7.2: Heat island effect - roof
posted by RASHID HAMEEN on Mar 25, 2010, 5:29 am

What if we apply a paint, for instance lets say we apply White color paint which is not a specific reflective coating on our roof. Will we able to claim the credit?
If not, do we...

Last reply: RASHID HAMEEN, Mar 26, 2010, 12:09 am

Existing building does not meet minimum energy efficiency

EBOM-2009 EAp2: Minimum Energy Efficiency Performance
posted by Karen Stewart on Mar 23, 2010, 4:52 pm

I have a client that has millions of square feet under roof. In 2006 they built a state of the art office/cooking lab building, designed for LEED NC 2.2. However they did not complete the LEED...

Last reply: Karen Stewart, Mar 25, 2010, 7:39 pm

preferred parking?

NC-2009 SSc4.4: Alternative transportation - parking capacity
posted by Leticia SooHoo on Mar 25, 2010, 4:56 pm

I am working on a project in an urban area which only has street parking and no designated parking to serve the new building. in order to qualfy for SSc4.3 and SSc4.4, the owner (which is the...

EA Credit 1

NC-2009 EAc1: Optimize Energy Performance
posted by Darin Frick on Mar 14, 2010, 9:45 pm

I have a project in which an auto repair garage is required to be ventilated at 1.5 CFM per square foot. The quantity of exhaust air is significant. In order to maintain habitable temperatures...

Last reply: David Posada, Mar 25, 2010, 4:43 pm

Building Classification

EBOM-2009 EAp2: Minimum Energy Efficiency Performance
posted by Mark Westover on Mar 25, 2010, 2:02 pm

We are working on a building for a private university. The building has classrooms, laboratories, offices, conference rooms and a small deli. From what I have read I believe it is an office...

Last reply: Jenny Carney, Mar 25, 2010, 2:35 pm

HCFCs and HFCs still meet Refrigerant prerequisite (EA PR3)?

CI-2009 EAp3: Fundamental Refrigerant Management
posted by George Boue on Mar 25, 2010, 10:59 am

A Credit Interpretation Ruling from 1/12/2009 indicates that since R22 is an HCFC that it meets the Refrigerant prerequisite. But I read somewhere (and now I can't find it) that CIRs before a...