Hi -My building is an industrial site. They use substantial potable process water to "waterproof test" assembled product. I am presuming this does not need to be included here or in WEC2? Can someone verify? (Efforts to reuse process water are underway - albeit as a separate project/possible innovation credit.) Thank you!
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Tristan Roberts
RepresentativeVermont House of Representatives
LEEDuser Expert
11478 thumbs up
March 26, 2010 - 11:03 am
Yes, this is process water that is not covered by the credit. In the words of the credit language, "Fixtures and fittings included in the calculations for this credit are
water closets, urinals, showerheads, faucets, faucet replacement
aerators and metering faucets."I think your other efforts to reuse it sound really good, though. And perhaps they could help you with WEc3 and/or WEc4?