EnergyStar in other countriesCI-2009 EAc1.4: Optimize energy performance - equipment and appliancesposted by Derek Fung on Dec 8, 2010, 11:03 pm
This old question again but with a new twist: As a project in China, all my project IT equipment checks out as EnergyStar due to using Dell and HP equipment. The only thing not compliant are the... Last reply: Tristan Roberts, Nov 20, 2011, 10:37 pm |
|
C&S building with partial occupancy during constructionCS-2009 IEQc3: Construction IAQ management plan - during constructionposted by Rubén M. R. on Aug 12, 2011, 6:22 pm
Our 23-story building is about to start partial occupancy at floor 12th. The building's... Last reply: Tristan Roberts, Nov 20, 2011, 10:35 pm |
|
Scheduling for CSCS-2009 IEQc3: Construction IAQ management plan - during constructionposted by BH . on Jul 12, 2011, 4:43 am
Dear all, we are making Core Shell project. Is it necessary to take into consideration flush out procedure during preparation of... Last reply: Tristan Roberts, Nov 20, 2011, 10:30 pm |
|
Regional Materials- raw materialNC-2009 MRc5: Regional Materialsposted by Felipe Duran on Oct 7, 2011, 12:35 pm
Hello, we are working on a project that aims to get the LEED NC-2009 certification. We used a stone removed from the site to compose some walls, and therefore has no cost. How this material could... Last reply: Nadav Malin, Nov 20, 2011, 10:21 pm |
|
PVmodules for generate of onsite renewable energy and RECNC-2009 EAc2: On-Site Renewable Energyposted by Florian Schmidtchen on Nov 17, 2011, 9:15 pm
For a NC manufacturing project we have been aproached by a company who would mount pv-modules on the building roof and sell them to building owner at no cost premium. Last reply: Florian Schmidtchen, Nov 20, 2011, 10:20 pm |
|
LEED CI Retail- Restaurant Kitchen EquipmentCI-2009 MRc4: Recycled Contentposted by Susie Spivey-Tilson on Nov 17, 2011, 4:26 pm
We are doing the MRc4 and MRc5 calcs for a restaurant i that is using the LEED CI 2009 Retail rating system. It is not clear to us whether or not we have to use the kitchen equipment... Last reply: Tristan Roberts, Nov 20, 2011, 10:19 pm |
|
Adaptive ReuseNC-2009 MRc1.2: Building reuse - maintain interior nonstructural elementsposted by Christine Robbins-Elrod on Aug 1, 2011, 3:51 pm
We're working on the adaptive... Last reply: Tristan Roberts, Nov 20, 2011, 9:44 pm |
|
Option 2: Stream Protection PlanNC-2009 SSc6.1: Stormwater design - quantity controlposted by Robert Thuston on Aug 2, 2011, 5:23 pm
I apologize if the requested information is included on this site but I have not seen it to this point. Can anyone give me a definition of what constitutes a stream channel? We are looking at a... Last reply: Tristan Roberts, Nov 20, 2011, 9:31 pm |
|
what is the difference between? and how could i measure???General forumsposted by ola shunnar on Nov 19, 2011, 6:29 am
what is the difference between the Gross square footage undergoing initial fit-out;... Last reply: Tristan Roberts, Nov 20, 2011, 9:08 pm |
|
Not Eligible for ENERGY STAR rating- Case 2 option 1 calculatorEBOM-2009 EAc1: Optimize Energy Efficiency Performanceposted by gwenedd murray on Oct 26, 2011, 1:08 pm
Our project is below 5,000sf which makes it automatically not eligible for an ENERGY STAR rating. There are two distinct space types, office + K-12 classroom. Based on this information, the... Last reply: Jenny Carney, Nov 20, 2011, 10:42 am |