Option 4 for non residential project 2003 ITE study

NC-2009 SSc4.4: Alternative transportation - parking capacity
posted by Florian Schmidtchen on Nov 7, 2010, 11:05 pm

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up November 12, 2010- 12:12 pm Robert, about the form question, I would check that your form is not "BETA" and ask GBCI for help via the feedback link.I couldn't answer your second question offhand. There is a lot of data in the ITE study. We reviewed it here. Log in or register to post comments ...

Last reply: Tristan Roberts, Nov 12, 2010, 12:12 pm

Hardscape minimum area

NC-2009 SSc7.1: Heat island effect - nonroof
posted by javier bolanos zeledon on Nov 10, 2010, 7:30 pm

that the industrial plant has a parking lot. Technically it will be out of my LEED boundary. SSc7.1 ...

Last reply: Tristan Roberts, Nov 12, 2010, 12:20 am

Installation Dates for LEED On-line

EBOM-2009 EAc5: Enhanced Refrigerant Management
posted by Andrew Barnes on Nov 1, 2010, 4:29 pm

Good day everyone. For our project site we have listed all of the units, calculated all of the leakage rates, etc. However there are a few of our units that do not have an accurate (precise day/month/year) installation date- and no one around the place ca...

Last reply: Tristan Roberts, Nov 11, 2010, 11:58 pm

Commissioning of On-Site Renewable Energy Systems

NC-2009 EAc3: Enhanced Commissioning
posted by Lauren Sparandara on Oct 21, 2010, 4:03 pm

I'm wondering my best approach moving forward with this reviewer and all others really. I don't really want to just provide a clarification because I want zero chance that it'll go to appeal...

Last reply: Lauren Sparandara, Nov 10, 2010, 1:59 pm

How Sophisticated Should Functional Tests Be?

NC-2009 EAp1: Fundamental Commissioning of Building Energy Systems
posted by Omer Moltay on Sep 5, 2010, 6:22 am

Dear All, Our CxA has produced functional tests that are simpler than we have expected. Our expectations were in line with sample tests found in ASHRAE guidelines or the peci.org website. The CxA tells us that for LEED simpler tests are OK, where only the result of the test as "COMPLIANCE" or "NON COMPLIANCE" are presented on the test forms. We would appreciate your comments on this. EAp1 ...

Last reply: Al Tibbs, Nov 10, 2010, 8:36 am

Frequency of Inspections

EBOM-2009 EAc2.3: Existing building commissioning - ongoing commissioning
posted by Maria Unruh on Nov 8, 2010, 5:06 pm

Pierce Holstrom Director of Engineering Environmental Building Strategies LEEDuser Basic Member 69 thumbs up November 8, 2010- 5:34 pm Ben, A lot of the ongoing commissioning items typically feed into a buildings normal operating plan. Checking calibration of thermostats, confirming supply temperatures, confirming functionality of lighting controls... Are the retro- commissioning items you are referring to similar to an outside air balance or another larger maintenance service? Log in or register to post comments Maria Unruh Electrical Engineer Antella Consulting Engineers LEEDuser Basic Member 72 thumbs up...

Last reply: Pierce Holstrom, Nov 8, 2010, 7:44 pm

Great analysis

General forums
posted by Leticia SooHoo on Nov 8, 2010, 12:13 pm

Thank you for the buildinggreen post. I work for a company that does a lot of new building Cx, so I would like bring up that that are some pretty major updates on the Cx requirements too, such as more systems required to be commissioned. I see that as a step forward to make LEED more stringent, resulting in better performing buildings. ...

IEQc8.2 limitations on number of vision panels?

NC-2009 IEQc8.2: Daylight and views - views
posted by Matt Napolitan on Nov 4, 2010, 2:21 pm

Diaa Madkour Architect LEEDuser Basic Member 39 thumbs up November 8, 2010- 8:30 am Dear Matt, Mentioned in Leed reference 2009 for new construction, on page 568 in Calculations section: "The line of sight can pass through 2 interior glazing surfaces but not through doorways with solid doors." So i believe this would be a clue that glazing partitions shouldn't exceed 2. Log in or register to post comments ...

Last reply: Diaa Madkour, Nov 8, 2010, 8:30 am

Multi-floor tenant- LEED CI project on single floor

CI-2009 SSc3.2: Alternative transportation - bicycle storage and changing rooms
posted by Susan M. Kaplan on Oct 25, 2010, 6:02 pm

only the project's FTE to the existing bike storage and showers (not the client's total FTE within the building) or else we begin to toe the line in not complying with MPR#2. We will also need...

Last reply: Susan M. Kaplan, Nov 1, 2010, 10:27 am

Rainwater harvesting Calcs.

NC-2009 WEc2: Innovative Wastewater Technologies
posted by Nelina Loiselle on Oct 28, 2010, 3:41 pm

Tristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up October 29, 2010- 5:24 pm I think the range is so wide because it depends a lot on your system—what kind of roofing or collection surface, how it's collected, etc. Is there someone designing your system who can provide input? Log in or register to post comments ...

Last reply: Tristan Roberts, Oct 29, 2010, 5:24 pm