CxA from early-design/peer review team?
CI-2009 EAc2:Enhanced Commissioningposted by Frances Yang on
Does anyone know if the CxA would be allowed to come from the same firm as the team that performed design up through 100%DD and then peer review of the design-build trades that took over desig
CxA contract
CI-2009 EAc2:Enhanced Commissioningposted by Noriko Nagazumi on
Hi all, From the LEED Online form: "Upload EAc2-2.
Late involvement by CxA.
CI-2009 EAc2:Enhanced Commissioningposted by Charles Nepps on
The Owner dragged his feet and did not bring a Commissioning Agent on board until after the construction documents were complete, and construction started.
CxA's commissioning activities
CI-2009 EAc2:Enhanced Commissioningposted by Bilge Ceylan on
The owner in my CI project is planning to appoint the operations and maintenance (O&M) firm as the CxA to achieve this credit.
Enhanced Cx -CxA in an Integrated Project Delivery IFOA format?
CI-2009 EAc2:Enhanced Commissioningposted by Margaret Montgomery on
In a contractual situation where the contractor, owner and architect are bound in a single contract, who is able to hire the CxA for enhanced commissioning?
Contractual Relationship
CI-2009 EAc2:Enhanced Commissioningposted by Brian Smith on
The owner is looking for CI-2009 Enhanced Cx on a project. The CxA was originally contracted through the GC as they were not a prequalified vendor of the Owner.
Training operating personnel training verirfication
CI-2009 EAc2:Enhanced Commissioningposted by Karina Hanyzewski on
Hi there!, I have a question regarding this requirement for EA Enhanced Cx. The Tenant is pursuing a LEED CI certification in a non-LEED Shell bldg.
Commissioning of Process Equipment
CI-2009 EAc2:Enhanced Commissioningposted by Graham Langton on
'Commissioning is required for all systems and equipment installed as part of the tenant’s project scope'...
Equivalence of local standards for commissioning tests
CI-2009 EAc2:Enhanced Commissioningposted by Bilge Ceylan on
We have a project outside the U.S., which is planning to attempt the enhanced commissioning credit. Would our project be required to follow the U.S.
CxA Allowed to be Hired by GC?
CI-2009 EAc2:Enhanced Commissioningposted by LUCY WILLIAMS on
Hi, Does the GBCI accept the Cx Agent for the Enhanced Commissioning credit to now be hired by the Contractor in a design-build scenario? In reading Interpretation #10244, it seems this is now all