Hi all, From the LEED Online form: "Upload EAc2-2. Provide the contract between owner and CxA ensuring CxA involvement post-construction." Would a contract between the LEED consultants and the CxA suffice instead of the contract stated above? Thanks in advance.
I do not see a problem as long as the contract path does not go through the Contractor. In other words, if the LEED Consultant has a contract to the owner it should be fine, I would just state that to the reviewers either by adding a note to the PDF or including the Owner to LEED Consultant contract along with the LEED Consultant to CxA contract.