Would a fieldhouse structure be included within the LEED Boundary
NC-v4 MPR2:Must use reasonable LEED boundariesposted by on
Our project is a community centre that includes a field house structure on site. The fieldhouse is partially enclosed, with the other portion covered by a canopy.
Minimum Program Requirements - Must use a reasonable site boundary: site + building
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Theresa Lehman on
This is a complex, multi-part question. An airport project is being phased and has multiple contracts. The scope includes replacing the runways and concrete around the terminals.
Existing building and extension building in one certification
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Helena Garcia on
In our team we are conducting a study for the construction of an extension of an existing building.
Phased Development - Demoing Building for Parking Lot
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Deb Favaretto on
Hi,
Emergency generator building
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Priscillia Champagne on
I am starting a project in which we are building a new addition to an existing hospital which will be approx. 30 000 m2 (considered separate building from existing hospital).
New addition with separate air distribution systems also feeding renovation portion of existing hospital
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Priscillia Champagne on
We are planning to register a new project for LEED certification, but we need to make sure that we can comply with the minimum program requirement #2 beforehand.
Is it applicable for a historic wall project to obtain LEED New Construction BD+C Certification?
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Amgad Khattab on
Is it applicable for a historic wall project to obtain LEED New Construction BD+C Certification?
Non-certified buildings in LEED boundary
NC-v4 MPR2:Must use reasonable LEED boundariesposted by marty seese on
I have a project that is all new construction. There are 3 buildings on the site. The main building which is what the owner wants to be LEED Certified. Another building is a shed building.
MPR 2 - different existing building on a railway station area
NC-v4 MPR2:Must use reasonable LEED boundariesposted by veronica andreis on
hello, we are facing a renovation of some buildings in an existing railway station area
Project Clarification Request: MPR2 & Rating System
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Olawale Taiwo on
A client has approached our team to review a project proposal intended for LEED certification, it is not a typical project, so some assistance at providing clarification per our concerns