Phase I for an Existing School

Schools-2009 SSp2:Environmental Site Assessment
posted by  John McFarland  on 

Do we need a formal Phase I assessment for a school remodeling project (major renovation)? The school site was a greenfield site when it was originally constructed approximately 50 years ago.

1
Thu Jun 2, 2011, 3:31 pm

Timeline for Site Assessment

Schools-2009 SSp2:Environmental Site Assessment
posted by  Brian Moran  on 

Does LEED 2009 require that the site assessment be performed within so many years of project construction?

1
Wed Feb 16, 2011, 11:02 pm

Can A project Team Perform that credit

Schools-2009 SSp2:Environmental Site Assessment
posted by  soha yamani  on 

I'm Having the same problem in a project in Egypt , as Ministry of Environment only provide Environmental Impact Assessment which is totally different from Environmental site assessment , and i cou

1
Tue Dec 17, 2013, 4:53 pm

Owned land for 150+ years

Schools-2009 SSp2:Environmental Site Assessment
posted by  Maura Adams  on 

The building is on a campus owned by the school for over 150 years. Before that, the land was part of a farming community. It's pretty much impossible for it to be contaminated.

1
Thu May 10, 2012, 4:32 pm

LEED for Schools, 2007 - Is there a 4th option?

Schools-2009 SSp2:Environmental Site Assessment
posted by  Lindsey Perez  on 

We are finalizing our submission for a LEED for Schools, v2007.

1
Tue Nov 27, 2012, 7:52 am

Alternative standards

posted by  Martin Mechtenberg  on 
1
Thu Sep 16, 2010, 8:16 am

Documentation of Remediation

Schools-2009 SSp2:Environmental Site Assessment
posted by  Laura Long  on 

We have a site we know to be contaminated and we are undertaking a remediation plan.

1
Sun Nov 20, 2011, 2:15 am

LEED Boundary for ESA

Schools-2009 SSp2:Environmental Site Assessment
posted by  Karen Richards  on 

If doing a 3,700 sf building in the corner of an existing 18 acre school campus, does the Phase I and possibly Phase II assessment need to be for the entire campus or just the area within the LEED

1
Mon Oct 22, 2012, 4:35 am

Alternative Compliance Path

Schools-2009 SSp2:Environmental Site Assessment
posted by  timothy thomas  on 

I am working on a project that at the initial project team meetings and scorecard review it was indicated that the Phase 1 ESA had been done and that there were no significant issues.

1
Sun Aug 27, 2017, 12:04 am

Lead Paint

Schools-2009 SSp2:Environmental Site Assessment
posted by  Adam Musante  on 

Generally speaking, is the presence of lead paint in an existing school from the 1950's cause for concern and must be addressed or else the prerequisite is not satisfied?

2
LFA, RESET ASP, WELL Faculty, LEED Fellow
Wight & Company
LEEDuser Expert
6 thumbs up