DES Option 2 - Clarification

NC-2009 EAc1:Optimize Energy Performance
posted by  FABIO VIERO  on 

Hi, we are working on a LEED NC 2009 project consisting of an office building, where the thermal energy (heating via hot water) is generated and distributed by means of a municipal grid (about 40 m

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon Oct 20, 2014, 3:37 pm

PU foam

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Emmanuel Pauwels  on 

Under what category would a 1-compnent mounting Polyurethane foam fall and consequently what would be the maximum VOC level allowed?

4
Mon Oct 20, 2014, 2:56 pm

No autosizing of equipment on proposed?

NC-2009 EAp2:Minimum Energy Performance
posted by  Saju Varghese  on 

Is there a reason why the equipment on the proposed can not be autosized?

2
b.i.g. Bechtold DesignBuilder Expert
LEEDuser Basic Member
581 thumbs up
Mon Oct 20, 2014, 11:13 am

Exhaust Fan Testing in a Laboratory

EBOM-2009 IEQp1:Minimum IAQ Performance
posted by  Alexis Thompson  on 

I am working on a laboratory project and we are gearing up to perform the exhaust fan testing internally.

6
Practice Leader - Sustainability
EUA
LEEDuser Expert
510 thumbs up
Fri Oct 17, 2014, 10:40 pm

What's in return?

General forums
posted by  Wing Ho  on 

As far as I know, the cost of $6000 a year is kind of like annual subscription fees for the LDP. After 12 months, you’ve to return the LDP back to USGBC in good shape.

2
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Fri Oct 17, 2014, 6:21 pm

Zero lot line existing building renovation

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Kim Shinn  on 

This project is a re-skin, and interior re-fit. Complete preservation of the structure. There was no site soil distrubance. What is required for SSp1 documentation?

4
Default Avatar
LEEDuser Basic Member
0 thumbs up
Fri Oct 17, 2014, 4:19 pm

On-site renewable energy

NC-2009 EAp2:Minimum Energy Performance
posted by  Lise Dannesboe  on 

Hi! We are trying to offset as much as possible from our electricity consumption with on-site PV.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Oct 17, 2014, 5:40 am

Cost!

General forums
posted by  Nelina Loiselle  on 

The cost is $6,000 a year! For a plaque!

9
Founder & CEO, LEED Fellow, BREEAM Fellow
BuildingWise LLC
LEEDuser Expert
224 thumbs up
Thu Oct 16, 2014, 8:20 pm

Sediment Basin

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Paula Hernandez  on 

Hello again, we are working on a project for which we are installing a sediment basin. According to EPA we could use the calculation of 3600 ft3 / acre drained to size it.

2
Regional Stormwater Leader
Arcadis North America
LEEDuser Expert
144 thumbs up
Thu Oct 16, 2014, 3:17 pm

Number of features required to be met?

Pilot-Credits EQpc78:Design for active occupants
posted by  Crista Shopis  on 

We have submitted this pilot credit for review, we included documentation for 7 of the 11 features listed in the credit description that qualify as satisfying the credit.

3
Sustainability Account Manager
Stok
LEEDuser Expert
177 thumbs up
Wed Oct 15, 2014, 7:51 pm