Campus setting uploading refrigerant data LEED letter templateNC-2009 EAp3: Fundamental Refrigerant Managementposted by John Covello on Apr 17, 2013, 5:56 am
Hello, This is a sort of how to LEED Online question. We have a resort campus setting. There will be several different sizes of guest villas as well as public spaces and staff facilities.... Last reply: Ante Vulin, Nov 4, 2013, 12:27 pm |
|
Use of CFC refrigerant for backup chillerNC-2009 EAp3: Fundamental Refrigerant Managementposted by Heather Dorer on Oct 1, 2013, 3:01 pm
We are working on a project that will be cooled by a pre-existing central plant. There is a chiller that contains... Last reply: Ante Vulin, Nov 4, 2013, 12:21 pm |
|
Heat Pipe RefrigerantNC-2009 EAp3: Fundamental Refrigerant Managementposted by Saju Varghese on Jul 30, 2013, 5:09 pm
Does heat pipe refrigerant need to be accounted for this credit? Thanks Last reply: Tristan Roberts, Nov 3, 2013, 9:16 pm |
|
HCFC123 or HFC410ANC-2009 EAp3: Fundamental Refrigerant Managementposted by edward deschapell on May 23, 2013, 10:57 pmTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11474 thumbs up November 3, 2013- 9:14 pm Edward, how are you defining "better"? According to the forum here, EAp3, either is equivalent. With the related credit, EAc4, the picture is a little more complicated. Log in or register to post comments ... Last reply: Tristan Roberts, Nov 3, 2013, 9:14 pm |
|
Documents/ details needed for alternative compliance pathNC-2009 EAp3: Fundamental Refrigerant Managementposted by Mark Meaders on Apr 4, 2013, 11:34 am
We have a project with a central plant with chillers that has R-11 refrigerant. An economic analysis has been performed by a 3rd party that states it is not economically feasible to replace the... |
|
Small HVAC Equipment & 0.5 lb ruleNC-2009 EAp3: Fundamental Refrigerant Managementposted by Nathan Lee on Mar 7, 2013, 2:41 am
Our project has removed all CFC based refrigerants on the main HVAC equipment. However we have some small HVAC equipment that use CFC Refrigerants. They are rated a 0.1 lb of refrigerant, so... Last reply: Ante Vulin, Mar 25, 2013, 1:56 pm |
|
HCFC 141b For Interior Pipe CleaningNC-2009 EAp3: Fundamental Refrigerant Managementposted by Roberto Meza on Jan 31, 2013, 7:47 pm
Is the complying with the prerrequisite in jeopardy for using HCFC 141b for cleaning the interior of the copper piping previous to installation? The system will be using R-410 for the cycle, but... Last reply: Ante Vulin, Feb 1, 2013, 10:40 am |
|
SF6 GASNC-2009 EAp3: Fundamental Refrigerant Managementposted by MARIA FERNANDA CORREA on Dec 13, 2012, 3:54 pm
The LEED NC V3 project we are working on has an electric system that requires an Electric Substation that has cells of medium tension which are protected with SF6 gas (sulfur hexafluoride),... Last reply: Ante Vulin, Dec 13, 2012, 5:07 pm |
|
Commercial Kitchen EquipmentNC-2009 EAp3: Fundamental Refrigerant Managementposted by Angie Allen on Nov 14, 2012, 9:48 am
We are working on a full service hotel project. For the commercial kitchen, it is my understanding that the permanent walk-in cooler and freezer units should be included in the credit. What... Last reply: Ante Vulin, Nov 26, 2012, 10:01 am |
|
custom-made refrigerator for EBOM projectNC-2009 EAp3: Fundamental Refrigerant Managementposted by Jorng-ren Chern on Oct 18, 2012, 4:08 am
I am working on EBOM... Last reply: Ante Vulin, Oct 18, 2012, 9:52 am |