Cutsheets for steel products

NC-2009 MRc4:Recycled Content
posted by  Raquel Clemente  on 

In our project it is possible to achieve 30% recycled content only considering the default 25% recycled content value for steel structural products. My question is if we must provide cutsheets for

5
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Thu Mar 29, 2018, 8:03 pm

Fenestration - Baseline vs. Proposed

NC-v4 EAp2:Minimum energy performance
posted by  Fábio Batista  on 

Hi all,

I have 3 questions to ask:

1.

1
Thu Mar 29, 2018, 6:06 pm

Documentation for Material Reuse?

NC-v4 MRc3:Building product disclosure and optimization - sourcing of raw materials
posted by  Megan White  on 

What is required for documentation of material reuse? In the Ref Guide (p.535), it says projects should track original location of the material before remove.

3
Thu Mar 29, 2018, 4:19 pm
2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Mar 29, 2018, 3:27 pm

How to conduct Cost-Benefit Analysis

EBOM-v4 EAc7:Renewable energy and carbon offsets
posted by  Hamzeh Saqer  on 

I just need to know how to conduct the cost-benefit analysis (step 6) for a PV array on-site owned by a third party.

0

Modeling DOA in Baseline for residential project

NC-v4 EAp2:Minimum energy performance
posted by  Saif Abdulameer  on 

I am working on a small hotel that is served by VRF units and DOA unit which dehumidify and reheat the OA for the guest rooms, when creating the Baseline system (system 2 for this project) should i

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Mar 29, 2018, 12:05 pm
2
Default Avatar
LEEDuser Expert
472 thumbs up
Thu Mar 29, 2018, 7:03 am

LEED ID+C CI commercial Interiors v4 water calc credit

CI-v4 WEc1:Indoor water use reduction
posted by  Robert Fernandez  on 

A little confused on this aspect of the credit....I was told buy a colleague that this credit can only apply to newly installed fixtures? and not base building restrooms that were not modified?

1
Thu Mar 29, 2018, 1:50 pm

Option 2 site area

CS-v4 SSc2:Site development - protect or restore habitat
posted by  Gail Napell  on 

Hi all

just confirming this is literally based on site area -i.e. our site is very small, so the cost is proportional. Thank you!

0

Distance between bicycle racks and functional/main entry

Warehouses-NC-v4 LTc6:Bicycle facilities
posted by  Agnieszka Rylska  on 

This credit requires provision of bicycle racks within 30m of any main/functional entry.

1
Thu Mar 29, 2018, 2:01 pm