Topic | Recent |
---|---|
LEED project Boundary different from Construction Documents?Healthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Gary Caraway on Jun 24, 2013, 9:11 am
Is it possible to have a LEED boundary that differs from the actual limit of disturbance shown in the construction documents? Last reply: RETIRED, Jul 23, 2013, 4:32 pm |
|
Project of 2 buildings in one territoryHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Laurence Theriault on Apr 3, 2013, 2:32 pm
I am working on a project who has two buildings in his land, but only one of them (an office building) will be in the process of becoming LEED NC. Both buildings are sharing the same parking and... Last reply: Tristan Roberts, Apr 30, 2013, 7:05 pm |
|
existing parking garage in the LEED project boundaryHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by yanghee pierce on Apr 19, 2013, 10:57 pm
I am working on a project that is a part of campus. This project will be located next to a 4-story existing parking garage shared by other adjacent non-LEED certified buildings. The question I... Last reply: Tristan Roberts, Apr 30, 2013, 7:02 pm |
|
Parking lot to be included in LEED boundary?Healthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Ilana Judah on Mar 22, 2013, 12:06 pm
We are working on a new LEED NC building that is part of a campus. The scope of work includes below ground parking underneath our building, as well as resurfacing of an adjacent parking lot. It... Last reply: Tristan Roberts, Mar 29, 2013, 2:28 pm |
|
Sum of LPBs = 100% of LCB?Healthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Zonda E. Team on Dec 28, 2012, 2:31 pm
Dear all, I find these below in contradiction. Supplemental Guidance to MPR revision 2 (1 Sep 2011) - MPR 3: Last reply: Lindsey Evans, Mar 21, 2013, 11:35 am |
|
Reasonable Site Boundary for LightingHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Carol Liebst on Dec 19, 2012, 3:22 pmTristan Roberts Representative Vermont House of Representatives LEEDuser Expert 11477 thumbs up March 21, 2013- 10:43 am Carol, can you post this question to our SSc8 forum? Thanks. Log in or register to post comments ... Last reply: Tristan Roberts, Mar 21, 2013, 10:43 am |
|
Core and Shell Renovation/Addition Parking not in ScopeHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Ed Clark on Jan 22, 2013, 1:55 pm
We are looking at a Core and Shell Renovation/Addition. We will pursue 2009 C&S and... Last reply: Tristan Roberts, Mar 21, 2013, 10:35 am |
|
LEED Site BoundaryHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Heather Holdridge on Jan 24, 2013, 6:49 pm
We are working on a Core & Shell project and our LEED site boundary includes a large parking lot and landscape area along with the building on the plot. We are working with a developer and... Last reply: Tristan Roberts, Mar 21, 2013, 10:34 am |
|
Underground car parkingHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by BH . on Feb 1, 2013, 9:58 am
Hi, we are dealing with new LEED hospitality project. The project will be constructed in two stages (two towers), with common parking under both of them constructed in the first stage. The... Last reply: Tristan Roberts, Mar 21, 2013, 10:29 am |
|
Project Boundary 2 buildings on site but only 1 certificationHealthcare-v2009 MPR3: Must use a reasonable site boundaryposted by Elke Malleier on Feb 8, 2013, 3:24 am
Hi experts, I would appreciate your advice on the follwoing, please. I am unsure to draw the project boundary in situation described below: Last reply: Tristan Roberts, Mar 21, 2013, 10:27 am |