Log in
Forum
Topic

Daylight Calculator

NC-v4.1 EQc7: Daylight
posted by Junaid Mujahid on Nov 20, 2024, 3:21 am

The LEED v4.1 requires area input for which the lux levels are within the range for 9am AND 3pm.

From my understanding of the credit language, it is required to average the 9am values for...

Last reply: Collin Robinson, Nov 20, 2024, 10:03 am

Reduced parking footprint attempted for Campus

NC-v4 LTc7: Reduced parking footprint
posted by Pham Kim Ngan on Nov 20, 2024, 4:28 am

Hi everyone, 

We have decided to classify our project as a campus project. The new building is part of Phase 2 of our development and will be constructed on land that has already been...

"Everything within the waterproofing membrane"

NC-v4.1 EQc2: Low-emitting materials
posted by James Keohane on Jun 24, 2020, 12:14 pm

The credit language states that materials which must meet the requirements are "everything within the waterproofing membrane."

The waterproofing membrane itself ( e.g....

Last reply: Allen Cornett, Nov 20, 2024, 2:38 pm

Cluster of small building connected by an exterior porch

LEED Guidance for Campuses and Multiple Buildings
posted by Summer Gorder on Nov 20, 2024, 11:56 pm

The project is a small artist sanctuary. The New Construction development contains multiple interconnected single-story buildings situated across the site connected by an exterior porch. Programs...

Last reply: Susan Di Giulio, Nov 21, 2024, 1:04 am

Demonstrating Green-e Equivalency for Green Power Purchased

CS-v4 EAc7: Green power and carbon offsets
posted by Yoyo Shek on Nov 20, 2024, 9:23 pm

Hi everyone,

We are working on a LEED BD+C Core and Shell project in Hong Kong and are planning to purchase International Renewable Energy Certificates (I-RECs) from ECOHZ to meet the...

Last reply: Marcus Sheffer, Nov 21, 2024, 12:43 pm

Requirement of Measurement for a new ventilation system

EBOM-v4 EQp1: Minimum indoor air quality performance
posted by Krithikha Muthukrishnan on Nov 22, 2024, 3:27 am

We are working on an existing factory project. It is mechnically ventilated in most spaces and those have been measured. However, the office spaces were conditioned through untiary ACs without...

Last reply: Dave Hubka, Nov 22, 2024, 6:57 am

Non-Air-condition Warehouse

LEED v4.1 Discussion Forum
posted by Sonny Calma on Nov 24, 2024, 9:44 am

Could you please clarify whether non-air-conditioned warehouses are eligible for LEED certification? Thank you.

VOC emission test report validity as LEED V4

NC-v4 EQp1: Minimum indoor air quality performance
posted by Christine Trinh on Nov 25, 2024, 2:14 am

Hello,

We have submiited...

Covered Basket ball court in roof

Warehouses-NC-v4.1 SSc3: Open space
posted by Sonny Calma on Nov 25, 2024, 10:44 pm

Does the covered basketball court on the roof qualify for open space credit?

Appendix 4. Table 1. Base Ratios for Parking

Warehouses-NC-v4.1 LTc7: Reduced parking footprint
posted by Sonny Calma on Nov 25, 2024, 10:50 pm

How do we calculate parking spaces using the Table for Base ratios for a warehouse with attached two-level office buildings? The predominant space is the warehouse.