Peak Transients

posted by  Abena Darden  on 
3
Wed May 8, 2013, 9:05 pm

LEED NC-2009 IEQc8.1: How to Average Multiple Tvis Values

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Jay Wierzbicki  on 

I am trying to calculate the resultant Tvis value of glazing when the overall value is not provided.

2
Wed May 8, 2013, 8:42 pm

Documentation of Natural Ventilation in PDF Template

NC-2009 EAp2:Minimum Energy Performance
posted by  Marco Abdallah  on 

We have modelled our building which is equipped with hydronic heating and natural ventilation (no cooling) according to App D of the Advanced Energy Modelling Guide v2.0.

3
Wed May 8, 2013, 3:02 pm

Small study rooms- 2-3 rooms per thermostat

NC-2009 IEQc6.2:Controllability of Systems—Thermal Comfort
posted by  Katie Schulze  on 

I am working on a library that has tons of spaces that can meet the needs of individuals or multiple occupants. In the case of the small study rooms, I am qualifying them as multi-occupant rooms.

2
Tue May 7, 2013, 10:31 pm

Energy modeling Gross Surface / Net surface.

CS-2009 EAp2:Minimum Energy Performance
posted by  Alessio Zampaglione  on 

Section 1.2 Space summary in prerequisite EAp2 asks for GrossSquareFootage (GSF) of regularly and unconditioned zones.

10
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue May 7, 2013, 1:50 pm

Filling out EAp2 form

CS-2009 EAp2:Minimum Energy Performance
posted by  Ron Dean  on 

Hi everyone, I have the three following questions: 1. In the EAp2 form, I have to write the HDD and CDD for Lima, Peru.

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Tue May 7, 2013, 12:19 pm

Pilot Credit #44 Ergonomics Strategy - LEED User registration

Pilot-Credits EQpc44:Ergonomics approach for computer users
posted by  Cindy Davis  on 

I received a comment back from our LEED preliminary design review that the 'reviewer' is unclear if the project team representative (me) has registered with LEEDuser, since a completed survey has n

5
Associate Vice President
CallisonRTKL
LEEDuser Basic Member
16 thumbs up
Tue May 7, 2013, 2:05 am

Sub-metering in Option D

NC-2009 EAc5:Measurement and Verification
posted by  Alicia Villanueva  on 

Marcus Sheffer posted some months ago in this credit: "You will need to calibrate the model by energy end use on a monthly (and annual) basis. [...] Yes you would need to separate out the electric

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Mon May 6, 2013, 10:57 pm

MPR#6 - Option 1: Sharing data via Energy Star Portfolio Manager

CS-2009 EAc5.1:Measurement and Verification—Base Building
posted by  Ron Dean  on 

One of the projects I'm working on in Peru, is persuing the option 1 of MPR#6 (through Energy Star Portfolio Manager:ESPM) so we can get one EP point in EAc5.1. So, my questions are: 1.

3
Default Avatar
Sumac Inc.
LEEDuser Basic Member
20 thumbs up
Mon May 6, 2013, 6:36 pm

No new parking, can we still achieve Option 1?

NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehicles
posted by  Eamon Geary  on 

The project I am working on is a new facility on a pre-existing campus. There are is no new parking added and all new employees are expected to find parking spots on their own.

7
Mon May 6, 2013, 5:44 pm