posted by Jean Marais on Sep 28, 2010, 5:53 am

Does anybody know how to specify SPECIAL CIRCUMSTANCES and uploads so that the "Compliance Documented:" box turns to Y?

Last reply: Clint Newton, Dec 29, 2010, 8:40 am

Completing OA table with correct Ev value.

CI-2009 IEQp1: Minimum indoor air quality performance
posted by LarsonBinkley Employees on Nov 10, 2010, 11:03 am

ASHRAE 62's Ev value is determined by either the ASHRAE Standard 62 Appendix A (lowest calculated method value of the zone efficiency Evz) or per ASHRAE's Table 6-3 "System Ventilation Efficiency...

Last reply: Tristan Roberts, Dec 29, 2010, 8:33 am

Upload whole system manual?

NC-2009 EAc3: Enhanced Commissioning
posted by Jorng-ren Chern on Dec 29, 2010, 7:34 am

The EA C3 credit form require us to upload system manual.

The project I am working is a large clean room project. The capacity of the HVAC system is huge and so are the system manuals. My...

Last reply: Scott Bowman, Dec 29, 2010, 8:33 am

VOC Methodologies

CS-2009 IEQc4.2: Low-emitting materials - paints and coatings
posted by Carmelito Tatlonghari on Sep 8, 2010, 4:57 am

Which methodology for analyzing...

Last reply: Reinhard Oppl, Dec 29, 2010, 7:51 am

EMICODE Accepted by GBCI?

NC-2009 IEQc4.1: Low-emitting materials - adhesives and sealants
posted by Omer Moltay on Mar 29, 2010, 4:08 pm

What about European products for this credit? Most of them are certified by EMICODE (as ug/m3 limits), which is more stringent than US standards. Many projects outside the US have to use paints...

Last reply: Reinhard Oppl, Dec 29, 2010, 7:37 am

Applying ASHRAE 62.1 to an existing building

NC-2009 IEQp1: Minimum indoor air quality performance
posted by Jennifer Wehling on Apr 8, 2010, 7:12 pm

We are doing a major renovation on an existing building. The project is seeking LEED NC certification and we are having trouble interpreting how the ASHREAE 62.1 standard needs to be applied to...

Last reply: Tristan Roberts, Dec 28, 2010, 11:37 pm

Is garbage truck parking counted at waste hauler facility?

NC-2009 SSc4.4: Alternative transportation - parking capacity
posted by Kendal Neitzke on Dec 9, 2010, 10:22 am

The project in question is an existing site for an existing garbage truck maintenance facility where the existing maintenance facility is being replaced with a new building. There are additional...

Last reply: Tristan Roberts, Dec 28, 2010, 11:28 pm

Option 1 flush out- Path 1

Schools-2009 IEQc3.2: Construction IAQ management plan - before occupancy
posted by Keelan Kaiser on Dec 15, 2010, 4:42 pm

Working on a school that will be completed by June 1, moving furnishings in July 1, and people in August. We have the month of June for flush out, hypothetically. We want to chase this credit,...

Last reply: Tristan Roberts, Dec 28, 2010, 11:08 pm

Example Roof Maintenance Program.

EBOM-2009 SSc7.2: Heat island effect - roof
posted by Jorge Lopez de Obeso on Dec 8, 2010, 12:28 pm

Do any of you guys have a complete roof maintenance program that can be shared? I'm not sure if the document needs to be as simple as it sounds or would need to have a number of specifications....

Last reply: Tristan Roberts, Dec 28, 2010, 10:58 pm

Limit Boundary-

NC-2009 SSp1: Construction Activity Pollution Prevention
posted by gabriel Morales on Dec 6, 2010, 5:42 pm

The project is located on a 2.67 ha L-shaped site and it consists on the following:
• 4 underground levels of parking
• 3 levels of retail (covering the entire site)
• 3 towers...

Last reply: Tristan Roberts, Dec 28, 2010, 9:45 pm