Using Chilled Water Pump similar to ASHRAE 90.1NC-2009 EAp2: Minimum Energy Performanceposted by Michael Wahjudi on Aug 16, 2016, 2:33 am
Hi, we have development where the Chiller Plant is serving three buildings. Due to of the distance of the building, the Chilled Water pump head is quite high and we required to install Chilled... Last reply: Marcus Sheffer, Aug 25, 2016, 9:16 am |
|
PVC Welding CementNC-v4 EQc2: Low-emitting materialsposted by Kerry Honsinger on Aug 16, 2016, 1:33 pm
Anyone come up with a PVC Welding Cement that meets the CDPH Standard Method v1.1 -2010 emissions requirement? Last reply: Sophie Kerr, Jun 1, 2020, 2:14 pm |
|
Denied EAp2NC-2009 EAp2: Minimum Energy Performanceposted by Charalampos Giannikopoulos on Aug 18, 2016, 12:57 am
After two rounds of review our model was denied because according to the reviewer’s comment it still “it remains unclear whether the energy savings modeled for space heating are justified”. The... Last reply: Monique Belmer, Aug 25, 2016, 11:42 am |
|
Wood pellets as a Renewable energy sourceNC-2009 EAc2: On-Site Renewable Energyposted by Vassil Vassilev on Aug 31, 2016, 8:04 am
We are at conceptual design stage for a new school building. The building will have its own boiler plant with oil fired burners as the only possible option available in the region. Last reply: Ward Miller, Sep 27, 2016, 11:09 pm |
|
Heat Recovery in the Baseline SystemsCS-2009 EAp2: Minimum Energy Performanceposted by Ciaran McCabe on Sep 2, 2016, 9:49 am
For HVAC systems that consist of Fan Coil Units with Air Handling Units providing 100% Outside air - constant volume (based on the min ASHRAE 62.1 requirements) - Will the baseline systems... Last reply: Marcus Sheffer, Sep 15, 2016, 9:10 am |
|
Structure and EnclosureNC-v4 MRc3: Building product disclosure and optimization - sourcing of raw materialsposted by Jon Clifford on Sep 10, 2016, 10:15 am
A discussion on the BPDO-EPD forum (http://www.leeduser.com/comment/redirect/66396) has started me thinking about how to treat... Last reply: Dionisio Franca, Sep 30, 2018, 9:28 pm |
|
Operating energy performanceNC-v4 MRc1: Building life-cycle impact reductionposted by Noriko Nagazumi on Sep 13, 2016, 9:05 pm
On the FAQ of this page the following is written: How does the LCA consider operating energy? Isn’t that going to be the biggest source of environmental impacts? Depending on the... Last reply: Dionisio Franca, Oct 19, 2016, 1:39 am |
|
postponing a construction creditLEED Reviews: Appeals, Design/Construction Submittals, and moreposted by Omar Elrawy on Sep 18, 2016, 9:21 am
I need to know what if I decide to submit sum, and not all, of the construction credits during construction preliminary submittal, and postpone some others for the construction final submittal.... Last reply: Sara Goenner Curlee, Sep 29, 2016, 2:01 pm |
|
Emergency PowerCS-2009 EAc5.1: Measurement and verification - base buildingposted by Brightworks Sustainability on Sep 19, 2016, 7:30 pm
The engineer on my project is asking what exactly needs to be submetered and I'm having difficulty answering just because I'm not as familiar with the credit details. They plan to monitor... Last reply: Marcus Sheffer, Sep 23, 2016, 10:28 am |
|
Definition of main entranceNC-v4 LTc6: Bicycle facilitiesposted by ABDUL MUTHALIB MOHAMED on Sep 21, 2016, 12:24 am
In the LEED v4 reference guide, it is given that the bicycle storage should be provided within 100' of the main entrance. Is it main entrance of the project building or project site? Last reply: Jose Romo, Apr 30, 2020, 11:06 am |