Enhanced CX 'Design Firm'NC-2009 EAc3: Enhanced Commissioningposted by Julianne Laue on Feb 18, 2011, 12:03 pm
If a firm is a AE firm and are signing the arch drawings, but not involved in MEP...can an engineer in the firm be the CX? Last reply: Keith Steurer, Mar 30, 2011, 4:20 pm |
|
STC ratings for ceiling and floors?Schools-2009 IEQp3: Minimum Acoustical Performanceposted by Tyler Barter on Mar 30, 2011, 9:16 am
hi, Last reply: Daniel Hicks, Mar 30, 2011, 3:20 pm |
|
Use CO2 Measurement to meet Prereq RequirementEBOM-2009 IEQp1: Minimum indoor air quality performanceposted by Eric Tu on Mar 29, 2011, 2:55 pm
Hello; Out BAS does not measure air flow (CFM), but, it does measure Return Air and OA C02 values. Can this PreReq be met using... Last reply: David Hubka, Mar 30, 2011, 1:51 pm |
|
Separate Trash & Recycling AuditsEBOM-2009 MRc6: Solid waste management - waste stream auditposted by Alexis Thompson on Mar 30, 2011, 1:31 pm
If a project has 2 separate haulers (one for trash, and one for recycling), then is it necessary to conduct both audits at the same time? Will the credit be denied/pending if the trash audit was... Last reply: Jason Franken, Mar 30, 2011, 1:50 pm |
|
Bike storage for residents with disabilities?NC-2009 SSc4.2: Alternative transportation - bicycle storage and changing roomsposted by Stefania Minotti on Mar 22, 2011, 9:53 am
I’m presently working on a mid-rise residential social housing building with 5 stories and 76 units. 67 of these apartments are 1 bedroom and 9 are two bedroom. According to the guide I need to... Last reply: Jonathan Weiss, Mar 30, 2011, 1:25 pm |
|
SamplingPilot-Credits PC36: Compartmentalizationposted by Aaron Gary on Mar 29, 2011, 7:07 pm
If a multifamily project (based on Green Rater/Builder experience) is approved for sampling by the USGBC will sampling be allowable for achieving this credit as well or will every unit have to be... Last reply: Asa Foss, Mar 30, 2011, 9:30 am |
|
Items to be implemented for EAc2.2EBOM-2009 EAc2.2: Existing building commissioning - implementationposted by Mark Campbell on Mar 22, 2011, 12:29 pm
It is clear that the low cost/no cost items uncovered during the investigation phase in EAc2.1 must ALL be implemented to satisfy the requirements of EAc2.2. My Question: Must ALL of the... Last reply: David Hubka, Mar 30, 2011, 7:36 am |
|
Space Summary- Table EAp2-1 Space Usage Type?Schools-2009 EAp2: Minimum Energy Performanceposted by Renee Shirey on Mar 29, 2011, 5:56 pm
In this Table, are we supposed to list EVERY room in the building, or group similar rooms to together? This table seems a lot like what is in PI f3 (Table PI f3 Space Usage Type) - but that one... Last reply: Marcus Sheffer, Mar 29, 2011, 6:07 pm |
|
Determining complianceNC-2009 SSc6.2: Stormwater design - quality controlposted by Tiago e Silva on Mar 10, 2011, 7:50 am
I’m working on a Project in Portugal, which consists in a 13.400m2 site, with 6000m2 rooftop (harvests rain), 2500m2 green roof, 2735m2 of gardens, 306 m2 of planters and 1840m2 of impermeable... Last reply: Amy Rider, Mar 29, 2011, 5:07 pm |
|
Removal % in LEED reference guide table.NC-2009 SSc6.2: Stormwater design - quality controlposted by Emmanuel Pauwels on Mar 17, 2011, 7:47 am
If I understand correclty, we can use the table in the reference guide with several BMPs to determine the removal efficiency. In this table however there are 2 values : average TS removal % and... Last reply: Amy Rider, Mar 29, 2011, 4:42 pm |