EQc3, EQc5 and filtration requirements

NC-2009 IEQc3.1:Construction IAQ Management Plan—During Construction
posted by  Steve Loppnow  on 

I'd like to confirm that if a project is pursuing EQc5, that they must use MERV 13 filters for flush-out but can still use MERV 8 filters on equipment that is operated during construction.

3
Thu Jun 5, 2014, 2:55 pm

Projects outside the US

CI-2009 EAc4:Green Power
posted by  Mike D  on 

The project is located outside the US where Green-e suppliers are not present. The project is thus looking at buying Green-e RECs.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Jun 5, 2014, 1:30 pm

Electric Instantaneous water heater

NC-2009 EAp2:Minimum Energy Performance
posted by  CT G  on 

Hi, The design team is specifying an electric instantaneous water heater on a project we are working with.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Wed Jun 4, 2014, 3:57 pm
5
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Wed Jun 4, 2014, 2:07 pm

MERV 13 filtration required? Need some opinions here...

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  David Gibney  on 

In order to comply with LEED IEQc5, do we need to provide MERV-13 filters for the supply air of a very large warehouse? The warehouse is expected to be “regularly” occupied.

2
Partner, Architecture & Sustainability
DIALOG
LEEDuser Premium Member
449 thumbs up
Wed Jun 4, 2014, 9:57 am

Group certification and single entrance

NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Rooms
posted by  Renaud Gay  on 

Hello everyone, One question regarding the Group certification.

2
Integrated Design & LEED Specialist
SERA Architects
LEEDuser Expert
1361 thumbs up
Wed Jun 4, 2014, 6:38 am

DES Option 2

CS-2009 EAp2:Minimum Energy Performance
posted by  BH .  on 

We are dealing with the project served by DES.

9
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jun 3, 2014, 3:14 pm

Req for heating & cooling in line with baseline when not in prop

NC-2009 EAc1:Optimize Energy Performance
posted by  Victoria Watson  on 

Hi, I am not quite sure how to comply with Appendix G requirement to heat & Cool all conditioned/indirectly conditioned spaces and use baseline system where not designed whilst still staying tr

5
Tue Jun 3, 2014, 2:44 pm

DES Option 2

NC-2009 EAc1:Optimize Energy Performance
posted by  BH .  on 

We are dealing with the project served by DES.

5
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Jun 3, 2014, 2:42 pm

Green e certified equivalence

CS-2009 EAc6:Green Power
posted by  R Jones  on 

We have an international project which will engage on a green power tariff with its supplier (indefinitely so not worried about the 2 year issue) Q: has anyone had any experience of internationa

3
Tue Jun 3, 2014, 2:11 pm