EAp2/EAc1- Case 2 Option 2b

EBOM-2009 EAp2: Minimum Energy Efficiency Performance
posted by Peter Locke on Apr 19, 2013, 4:41 pm

We are submitting a museum bldg and have had confirmation from...

WEc2 vs. Pilot Credit 10

Pilot-Credits WEpc10: Sustainable wastewater management
posted by Anna Korinkova on Apr 23, 2013, 5:51 am

Hi all,
do I understand correctly that the pilot credit allocates WEc2 requirements to Option 1 and Option 2 and adds Option 3?
My project reduces use of potable water of 47 % just by...

invidually buildings ceritifcation vs multiple buildings/ campus

LEED Guidance for Campuses and Multiple Buildings
posted by Muhammad Faisal Azizullah Jaffar on Apr 24, 2013, 12:41 am

My project is based in Qatar and the total site area is around 13,000748 m2 of GFA comprising of 10,654 sqm of retail, 78,563 sqmof commercial office space including, 132sqm of atrium circulation...

Greywater recirculated

NC-2009 WEp1: Water Use Reduction
posted by Mike D on Apr 25, 2013, 5:26 am

Our water reduction due to fixtures and fittings only is 38%. We have recirculating greywater in the project that will be recirculated to toilets. This will bring our reduction to 42%. I know...

Average Pressure Differential Calculation- Underground Parking

CS-2009 IEQc5: Indoor Chemical and Pollutant Source Control
posted by Nathan Lee on Apr 26, 2013, 3:23 am

We have 6 Floors of Underground Parking on a high Multi-Use Tower. Total Project size is over 1,000,000 sqft and the parking areas are approximately 25,000 sqft to 30,000 sqft per floor.

...

Pilot Credit 10

Pilot-Credits WEpc10: Sustainable wastewater management
posted by Alicia Villanueva on Apr 26, 2013, 1:44 pm

Hallo,
My team and I have reduced water use in a project through high-efficient flush fixtures by 67%.
In addition, 100% of the water used for sewage conveyance is treated on-site to...

Questions

Pilot-Credits WEpc10: Sustainable wastewater management
posted by Lolita Wu on Apr 28, 2013, 6:26 am

Hi all,
We are working on a project that uses recycled wastewater and collected rainwater for toilet and urinals. As we can not meet the 50% water use reduction by just using water fixtures...

Cistern doesn't fulfull need, but there is no-potable backup

NC-2009 WEc1: Water Efficient Landscaping
posted by Sarah Picking on Apr 30, 2013, 11:09 am

If you can't prove that your cistern will satisfy the irrigation need every month, but the client has agreed to not have a potable backup (ie the cistern gets drained, and then the plants just...

Pilot Credit 10

Pilot-Credits WEpc10: Sustainable wastewater management
posted by Alicia Villanueva on Apr 30, 2013, 12:27 pm

Hallo,
My team and I have reduced water use in a project through high-efficient flush fixtures by 39%.
In addition, 100% of the water used for sewage conveyance is treated on-site to...

LEED Signage for display inside Gold certified office building

General forums
posted by Jeff Zunt on May 5, 2013, 3:54 pm

I'm looking for great examples of sign packages that were developed and displayed in buildings that identify the LEED credits achieved throughout the building and how they were achieved. Perhaps...