FAQs about EAp2 :

I have a mixed-use building and am wondering if it is possible to pursue the prerequisite through Case 1. How do we proceed?

We have a building that consists of two attached structures and it’s unclear if we have to consider it a single building or if it should be certified as two separate buildings and benchmarked accordingly. How should we proceed?

How long is an Energy Star label valid to use with a streamlined approach for Case 1?

Our building includes heavy process loads that significantly increase the overall energy use in the building. If we submeter these loads, can we exclude this energy use for benchmarking purposes?

We have installed submeters on our building but the utility bill includes energy use from several other buildings located on the same campus. How do we reconcile this during the LEED review process?

When is it possible to exclude up to 10% of the building from EAp2?

What do I do if the number of building occupants, operating hours, or vacant space changes during the performance period?

If you pursue the streamlined path for an Energy Star label, should the performance period for EAc6 match the 12-month time frame of the label?

How do I account for computers with multiple monitors on Portfolio Manager?

How should I treat vacant space on Portfolio Manager?

Our building includes a large laboratory space. Can our project benchmark under the Labs21 program?

We have an international project and the space type is eligible for an Energy Star rating. Can we pursue Case 1 to demonstrate compliance given the recently released alternative compliance paths for international projects?

We have a number of buildings on a single campus that we would like to certify at the same time. Is it possible to benchmark the buildings at the campus level?

View answers »

Forum discussion

EBOM-2009 EAp2:Minimum Energy Efficiency Performance

Energy Star Portfolio Manager

We are working on a multi tenant project and during our performance period the owner lost a large tenant. The tenant loss is not large enough to put the project in jeopardy of qualifying for EBOM certification, but large enough that the FTEs entered into EStar PM should be altered to obtain the true FTE energy use. Should we average the FTEs over the two years of data that we have in EStar? We have asked EStar this question, it took a very long time to get an answer and the answer did not help. Thank you!!

0

You rely on LEEDuser. Can we rely on you?

LEEDuser is supported by our premium members, not by advertisers.

Go premium for $15.95  »

Wed, 12/11/2013 - 19:12

Depending on the type of project you might find your answer here - http://portfoliomanager.supportportal.com/link/portal/23002/23010/Article/34288/How-do-I-account-for-my-office-property-s-vacant-space-in-Portfolio-Manager here - http://www.energystar.gov/buildings/sites/default/uploads/tools/pm_lp_guide.pdf?1e71-b60a or here - http://icma.org/en/icma/knowledge_network/documents/kn/Document/304708/Sustainability_Howto_Guide_Series__EPAs_ENERGY_STAR_Measurement_and_Tracking_Tool__Portfolio_Manager

Mon, 12/16/2013 - 22:23

Another EStar PM question...We have a data room in our building. Our plan is to carve out the data room from our LEED certification because it is less than 10% of the GSF of the building, has its own HVAC unit, is managed and paid for by the data room tenant and the tenant is not cooperative in the LEED process. Is it possible to carve this out of EStar PM also and then explain in a narrative to LEED the GSF <10% discrepancy or do we need to use Case 2 of EAp2/EAc1? It is my understanding that EStar will no longer allow data room exceptions. Thanks for any assistance!

Tue, 12/17/2013 - 14:36

Kelly, I don't think you can just ignore the area. Try looking here - http://portfoliomanager.supportportal.com/link/portal/23002/23010/Article/35187/I-m-getting-an-alert-that-I-do-not-have-an-associated-IT-energy-meter-when-in-fact-I-do-Why Here http://portfoliomanager.supportportal.com/link/portal/23002/23010/Article/35103/I-m-adding-a-new-data-center-to-my-property-Do-I-have-to-wait-a-year-to-get-a-score or here http://portfoliomanager.supportportal.com/link/portal/23002/23010/Article/34389/The-data-center-property-use-located-within-my-office-building-is-already-sub-metered-Can-we-use-this-information-to-enter-IT-Energy-Consumption-for-the-data-center-when-benchmarking-in-Portfolio-Mana

Thu, 08/28/2014 - 13:42

I have the same question that Kelly. I understand that when you want to perform an Energy Star score for a building, you can't remove data center consumption. But LEED EBOM also enables to remove 10% of the building total area for LEED certification (providing that this 10% are submetered and managed by a third party). According to my understanding, for LEED, you have to perform an Energy Star score not to the entire building but only for the 90% if you decide to exclude a 10% area. So I dont understand why it would be impossible to exclude the data rooms? I'm wainting for answers of USGBC but if you can give me information, it would be very helpful! Thanks!

Tue, 09/09/2014 - 23:05

Both LEED and ENERGY STAR have a rule in which 10% of the building may be excluded from either the LEED requirements or from the building profile in Portfolio Manager in certain situations. However, this rule is not applied the same way in LEED and in Portfolio Manager. The primary difference is that in order for the space to be excluded from Portfolio Manager, it must be a space type that cannot receive an ENERGY STAR score. Per LEED requirements, the space that is excluded from EAp2 is not required to be a space type that cannot receive an ENERGY STAR score. For example, for a building that is entirely office that has a data center space that is under separate management, that represents less than 10% of the gross square footage, that is separately metered, and in which the tenant is unwilling to share energy usage data, the project team may exclude the data center space from the building profile in Portfolio Manager (along with the energy usage associated with that space), even though that space is a ratable space type. Please note that if the data center is a part of or supports a larger space in the building under the same tenancy, unless both the data center and supported space are able to meet the exemption criteria they cannot be excluded. In this situation, the building would not be eligible to receive the ENERGY STAR but would be complying with LEED requirements for EAp2. While this exception is allowed, it is preferred that the entire building be included in Portfolio Manager.