Exemplary Performance for No Parking

NC-v4 LTc7:Reduced parking footprint
posted by  Risto Beatty  on 

If a project has no parking whatsoever, new or existing, can it claim exemplary performance for a 100% reduction?

7
Mon Aug 21, 2017, 6:06 pm

Use ASHRAE 90.1 Appx G for modeling 3-story residential building

ND-v2009 GIBp2:Minimum building energy efficiency
posted by  Mugdha Mokashi  on 

The scope of work for one of our ND project includes a 4 story residential building (new construction) and additions to 3 low-rise (3 storied) residential buildings.

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Fri Aug 18, 2017, 5:26 pm

Shades and blinds

NC-v4 EQc7:Daylight
posted by  Antonio Macedo Filho  on 

I'm working on an office project, and there's an atrium. We want to use a translucent and permeable tensioning fabric on the roof of this atrium. Could this structure be considered a shade?

3
Thu Aug 17, 2017, 2:41 pm

office building

Retail-NC-v4 WEc4:Water metering
posted by  Zahid Ahmed  on 

recently appointed as FM in commercial office building. what to do if we want to go for LEED certification. need details. thank you

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Aug 17, 2017, 11:17 am

Non-LEED-Certifiable Building on Site

Healthcare-v2009 MPR3:Must use a reasonable site boundary
posted by  Krissy Buck Flickinger  on 

Hello everyone- I have basically two questions in one, regarding how to treat additional buildings on your site. Project Background: I have an 880,000 SF site.

2
Project Architect
RSP Architects
LEEDuser Basic Member
1 thumbs up
Wed Aug 16, 2017, 9:52 pm

Using the calculator tab for MRc5 credit

NC-2009 MRc5:Regional Materials
posted by  Kavita K  on 

This is my first time handling LEED documentation for MR credits and I am confused as to how to use the calculator tab for MRc5.

4
Default Avatar
Environmentally Sustainable Design Assistant
Aurecon
LEEDuser Basic Member
2 thumbs up
Wed Aug 16, 2017, 1:37 pm

Occupancy rate for disabled

NC-2009 WEc3:Water Use Reduction
posted by  Mark JIN  on 

Our supplier is providing basin taps with different flowrates for normal washrooms and disabled washrooms. How can I determine the occupancy of the disabled to estimate water usage?

3
Tue Aug 15, 2017, 8:00 am

Temporary roof over seating on terrace

CS-2009 SSc7.2:Heat Island Effect—Roof
posted by  jesmin joseph  on 

Hi, We have a building with 80% of the terrace area is used as some seating place and also some sheet roof is planning to provide on that area.

3
Mon Aug 14, 2017, 6:31 pm

Parking garage ventilation - Proposed vs. Baseline

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Hi Markus, Following our correspondence as of Jul/13/2017, we've modeled the garage ventilation claiming some energy savings. We've provided explanation reflecting all details including all conside

9
Fri Aug 11, 2017, 1:43 pm

Credit Make-up Air Unit

NC-2009 EAp2:Minimum Energy Performance
posted by  John   on 

Can we claim the credit for Make-up air unit? or do we need to model it in Baseline same as proposed? How to show this system in Section 1.4?

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Fri Aug 11, 2017, 3:38 am