Forum quick links
Forms Update
posted by Rachael Vidulich on
I need to update my forms on LEED online as most of them are v01 and have "BETA" listed at the bottom.
Energy Modelling Issues
NC-2009 EAp2:Minimum Energy Performanceposted by Cynthia Estrada on
I am project admin for a V3-2009 NC project and wondered if anyone had issues with energy modeling software and accuracy of results with complicated/unique systems?
seashells considered recycled content?
CI-2009 MRc4:Recycled Contentposted by Dan Governile on
Can anyone tell me if seashells can be a recycled content in the manufacture of cement terrazzo countertops?
Re-submission for Design Review
posted by Madhura Dhayagude on
We are currently working on a project that had submitted documentation for Design review.We were not on board then. After the review, the project went on a hold for a period of almost 3 years.
Epoxy Flooring with ZERO VOC
NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systemsposted by Susan Morris on
I have a project with a large area of Epoxy Flooring, this epoxy contains 0% V.O.C.'s does it count as an inert material; or is testing required? Thank you
Reviewr's Comment is requesting labor and delivery
CI-2009 MRc4:Recycled Contentposted by Sarah Thompson on
In all my 40 LEED projects I have never included labor and delivery to a material's cost total.
Duct Sealant
NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealantsposted by Yaneth Galindo on
I used a duct sealant with VOC = 49 g/l and I am not sure if it complies with IEQ credit 4.1, because I do not know in which category it falls in the table.
Warehouse Office
EBOM-2009 IEQc3.5:Green Cleaning—Indoor Chemical and Pollutant Source Controlposted by Saul Pichardo, AIA on
My project has a 6,500sf office space serving a 207,000sf warehouse/distribution center (213,500sf total area).
Laboratory 90.1 Modeling
NC-2009 EAc1:Optimize Energy Performanceposted by Victoria Watson on
Hi, I am modeling a laboratory which has a small area of office space for LEED and wanted to check a couple of approaches: 1) The engineers have informed me that the lab has to be a once through sy
G3.1.10 (d) "Heating only System"
NC-2009 EAp2:Minimum Energy Performanceposted by Anil Bhari on
Based upon G3.1.10 (d) “Where no cooling system exists or no cooling system has been specified, the cooling system shall be identical to the system modeled in the baseline building” Does this mean