Pilot Credit 87 - Verified Construction and Demolition Rates
Pilot-Credits MRpc87:Verified Construction & Demolition Recycling Ratesposted by Patty Lloyd on
Documentation of this credit was easy because we are using a hauler who has a CORR certified facility that is near to our job. We tried this pilot credit once before and did not achieve it be
Social Equity Within the Community pilot credit
Pilot-Credits IPpc89:Social equity within the communityposted by Danielle Eke on
Has anyone pursued the Social Equity Within the Community pilot credit and would be willing to share their experience or any lessons learned?
SRI Values for Precast Concrete?
NC-v4 SSc5:Heat island reductionposted by Brian Salazar on
Hello - Has anyone found a published study or list of SRI values for precast concrete when used as a roof material, specifically as the top level of a parking structure?
Construction Waste Management - use of materials for shoring, etc.
NC-v4.1 MRp2:Construction and Demolition Waste Managementposted by Erik Heuler on
If a contractor uses demolished lumber as temporary shoring on a project does that count as material reuse or diversion from the landfill?
MERV 14 and WELL
Pilot-Credits INpc155:Design for Indoor Air Quality and Infection Controlposted by Chris Osterhoudt on
For projects pursuing WELL certification in tandem with LEED, MERV filtration requirements are already being met, and ventilation strategies are outlines in the Sequence of Operations as part of th
Baseline Energy Model - Outside Air Ventilation Rate for Zoo Spaces
NC-v4 EAp2:Minimum energy performanceposted by Mini Laird on
We would like to confirm our approach to determining the outside air ventilation rate for a Zoo project for the Baseline energy model, specifically for an animal holding area.
ASHRAE 90.1 Section 6.5.3
NC-v4 EAp2:Minimum energy performanceposted by Michael Abramson on
Good afternoon all,
Radon Requirements for LEED v4 - Residential/Dwelling Units
NC-v4 EQp1:Minimum indoor air quality performanceposted by Chris Wilson on
We are working on a five-story student dormitory including a partial basement area in EPA Radon Zone 1. Are we required to follow the guidance for 'residential only' projects in high-risk are
Commuter/Light rail station further than 0.5 miles from project boundary
CI-v4 LTc3:Access to quality transitposted by Aarohi Savani on
I'm working on a access to quality transit(table 2) that has a commuter rail station at 1.6 miles walking distance from the project boundary.
Student Dormitory: Institutional or Residential?
NC-v4 LTc6:Bicycle facilitiesposted by Dan Jaconetti on
Can a student dormitory be considered Institutional (Case 1) or does it need to be calculated as Residential (Case 2). Some people are saying that its housing so it must be residential howeve