Pilot-Credits SSpc82:Local food production
posted by  OSLEIDE WALKER  on 

Does anyone have any experience developing a successful Integrated Pest Management (IPM) Plan for this pilot credit. Do you know exactly what measures or components are required?

0

ECp2 and c1 - Location of this Addendum?

General forums
posted by  Michelle Bracewell-Musson  on 

Hello Tristan, My team has had a bit of a challenge trying to find "like" manufacturing buildings that are conditioned.

1
Tue Aug 29, 2017, 4:33 pm

Slab on grade and concrete piers

NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roof
posted by  David Browne  on 

I have a large building with an arena at the second level. I am retaining the slab on grade on the first level except for some small cuts to run piping.

1
Wed Jan 18, 2017, 4:38 pm

Enhanced IAQ Strategies - Hazardous Gases/Chemicals

NC-v4 EQc1:Enhanced indoor air quality strategies
posted by  Tom Martin  on 

Has the pressure differential requirement of at least 5 pascals for LEED v2009 IEQc5 Indoor and Chemical Source Pollutant Control been eliminated from the requirement of this credit?

1
Mon Aug 17, 2015, 10:04 pm

EAcp66 Community Contaminant Prevention- Airborne Releases

NC-v4 INc1:Innovation
posted by  Helene Lefkowitz  on 

Our project team found the Community Contaminant Prevention- Airborne Releases to be a great pilot credit to continue working toward a more pure indoor air quality.

1
Wed Dec 5, 2018, 7:13 pm

Form (V06) product data samples

CI-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Zachary Tetreault  on 

Does anyone know with the New Form (V06) do we no longer have to upload more than 20% of the product sheets?

1
Sat Aug 26, 2017, 10:32 pm

New and Renovation: How to Determine Points from Table 1

NC-v4 EAc2:Optimize energy performance
posted by  James Keohane  on 

I am working on a project that is approx. 24,600sf which includes 11,600s.f. of major renovation with 13,000s.f new construction.

1
Fri May 26, 2017, 1:46 pm

Showers in group projects

NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Rooms
posted by  Stacey Olson  on 

This piggy-backs to my previous comment about bike rack locations. Per the published Campus/Group Eligibility Credits & Prerequisites for LEED 2009, SSc4.2 - Alternative Transportation Bicycle

0

Recycled Water

CI-v4 WEc1:Indoor water use reduction
posted by  ESD Engineer  on 

The building our project is located in uses municipally supplied recycled water to serve the supply to the water closets and urinals. Can this be used to calculate additional savings?

1
Tue Aug 15, 2017, 9:09 pm

Building Reuse

NC-2009 MRc1.1:Building Reuse—Maintain Existing Walls, Floors and Roof
posted by  David Browne  on 

With regard to Credit MRc1.1-Exisitng walls, floors and roof: I have a building which has a fake mansard around its perimeter.

1
Mon Jun 1, 2015, 9:13 pm