Charger locations in assigned parking for condo tower
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Susan Di Giulio on
Hi, We are working on a campus project with luxury condo towers.
LEED Deliverables from EnergyPro - Purchased Campus Utilities
NC-2009 EAp2:Minimum Energy Performanceposted by Evan Friesen on
Hello, I am working on a project in Davis. The building utilizes campus (district) steam for heating and chilled water for cooling.
Inclusion of total building in density calculation
CI-v4 LTc2:Surrounding density and diverse usesposted by Deborah Stadler on
What happens when the 1/4 mile from the project boundary bisects a dense building? Can the whole building be included in the calculation? Only the part of the building that is in the 1/
Building Add-on to Design-Build Parking Structure
NC-v4 MPR2:Must use reasonable LEED boundariesposted by GBD Architects on
We are pursuing an office project that would be essentially an addition to a parking structure that is being built design-build just several months in advance of when our work would take place.
Where do you find the "Mitigated Design Storm Rainfall Volume" for the entire site (cu ft)?
EBOM-2009 SSc6:Stormwater Quantity Controlposted by bryan lauer on
For Miami-Dade County, FL.
In the SSc6 form, where do I find the "Mitigated design rainfall volume for the entire site (cu ft)? In the building
O+M Starter Kit for CI
CI-v4 INc1:Innovationposted by Kristen Magnuson on
Our CI project Owner is occupying 100% of the building, including core space. They are also responsible for operations and maintenance practices. However, they are do not own the building.
Service Sink Baseline flow
NC-2009 WEp1:Water Use Reduction—20% Reductionposted by Jorge Torres-Coto on
I have a project that includes mainly Vocational Classrooms. As such, each classroom has Service Sink for washing hands after each class (Diesel, Auto Mechanic, Carpentry, Welding, Sheet Meta
Treatment of Garages in calculating CWM Baselines
Homes-v4 MRc3:Construction waste managementposted by Kimberly Vermeer on
Small addition to existing building
NC-v4 MPR2:Must use reasonable LEED boundariesposted by Edmée Knight on
Our project is a small addition (<10% of total building GSF) to an existing building.
Fundamental Commissioning Timeline
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Todd Bundren on
I am working on a project where the Owner Project Requirements and Basis of Design were created at the appropriate times.