Post a question or comment
Location Filters
Filter by location
Forum
Topic
Replies
Recent

one product both meet two criteria in option2.

CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materials
posted by  Renaud Gay  on 

Dear All, for option 2 calculation, I have a question on it. My project is a CI retail project. They will use carpet which include recycled content.

8
Sun Apr 22, 2018, 7:09 pm

drainage area for sediment basin

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Hongyun Zhou  on 

when calculating the volume of sediment basin, what is the drainage area? Should I use footprint of the building or total land area of LEED boundary?

5
Mon Feb 12, 2018, 10:06 am

How to calculate the Tank size

NC-v4 SSc4:Rainwater management
posted by  Patrick Y P Lui  on 

I am working a hotel project with 6090 sq.m greenery + 14210 sq.m pavement and willing to get 3 points by Percentile of rainfall events (Option 1) - Path 2 98th Percentile.

0

What's the size requirement for a Data Center Project with LEED v4 BC+D and O+M?

EBOM-v4 MPR3:Must comply with project size requirements
posted by  Xiaoyu Cao  on 

Hi,

I see the minimum size requirements for BD+C and O+M is ,

"LEED BD+C and LEED O+M Rating Systems

1
Thu Nov 2, 2017, 4:12 pm
4
Project Director
WSP USA
LEEDuser Basic Member
381 thumbs up
Mon Oct 9, 2017, 10:19 am

Historic site

CS-v4 LTc3:High priority site
posted by  Jie Xiong  on 

Hi I am new to V4. There is a question about this credit. On the RG, page 75 further explanation, says that "project may......indicates has significant historic or cultural value".

1
Tue Nov 15, 2016, 11:48 pm

PAUs not serve the occupied areas

NC-2009 IEQp1:Minimum IAQ Performance
posted by  study topenergy  on 

A data center is applying for LEED-NC v2009. There are 5 PAUs (Primary Air Unit). 4 of them will serve the equipment rooms. One will serve the equipement rooms and office areas.

1
Tue Mar 24, 2015, 2:49 pm

Is this items means?

Credit Forums
posted by  shize zhang  on 

Is this item means onlly a building certified by ISO 50001 can apply for 1 credit in EA? Then how to apply for ACP? Thanks.

1
Mon Jan 4, 2016, 5:56 pm

DCV requirement for high-occupancy areas

CS-2009 EAp2:Minimum Energy Performance
posted by  Shenhao Li  on 

Hello! We have a canteen project in Shanghai. The building has three floors, total GFA is 64,067 square feet. The baseline HVAC system type is system 6.

1
Tue Apr 5, 2016, 2:48 pm

Questions on ASE and sDA assessment area

NC-v4 EQc7:Daylight
posted by  Jackie Cheung  on 

Hello everyone. May I ask 2 questions on option 1 in EQ credit-Daylight? A) Assuming a project go for option 1 in EQ credit Daylight.

0