A data center is applying for LEED-NC v2009. There are 5 PAUs (Primary Air Unit). 4 of them will serve the equipment rooms. One will serve the equipement rooms and office areas. Now, I am doing the calculation of mechanical ventilation. Should I only calculate the office areas (staffs work in these rooms), or should I do the calculation cover all the 5 PAUs?
You rely on LEEDuser. Can we rely on you?
LEEDuser is supported by our premium members, not by advertisers.
Go premium for
Dave Hubka
Practice Leader - SustainabilityEUA
LEEDuser Expert
545 thumbs up
March 24, 2015 - 10:49 am
if the equipment rooms can be defined as "inactive storage" than only the office areas need ventilation calcs.