Requirement of Measurement for a new ventilation system
EBOM-v4 EQp1:Minimum indoor air quality performanceposted by Krithikha Muthukrishnan on
We are working on an existing factory project. It is mechnically ventilated in most spaces and those have been measured.
FEES FOR BASEMENT AREA
posted by Subrota Roy on
Is it necessary to calculate the basement area when we calculate the gross floor area?For feea. If this area is not only used as parking but also used as some function as storage.
Measuring Chiller COP - LEED certification
CS-v4 EAp2:Minimum energy performanceposted by Shuvajit Batabyal on
Hello everyone.
Bicycle credit doubts
NC-v4 LTc6:Bicycle facilitiesposted by Deva venkat on
Hi team, i have doubts in bicycle credit.my project location is Bangladesh government using common road for two wheeler and four wheelers. Here how i get points in bicycle credit.
Regarding Embodied Carbon/LCA Optimization
NC-v4.1 MRc2:Environmental Product Declarationsposted by Nagaraj Sankar on
In this credit, How can I prove that my purchased material has compile with Embodied Carbon/LCA Action Plan or other impact reductions .
Question regarding Occupancy sensor
NC-v4 EAp1:Fundamental commissioning and verificationposted by Nagaraj Sankar on
How can we show and prove, here are the palces we gave an ocupancy and daylight sensor for manufacturing project? and Is there gudelines used to follow to place sensor on
Carbon emission for Electrical Energy and Natural gas
NC-v4.1 EAc2:Optimize Energy Performanceposted by SAMY Chamy on
Dear Concern
Our project is located in Bangladesh and we are looking for carbon emissions per unit of electricity production and 1 m3 of natural gas usage.
Filtration Requirement for a Evaporative Cooling System
NC-v4 EQp1:Minimum indoor air quality performanceposted by Krithikha Muthukrishnan on
Hi,
Certification Timeline for a registered Project
NC-v4 MPR3:Must comply with project size requirementsposted by Radhesh Sarkar on
Project is underconstruction and 60 % completion of gross project work. Now project is registered under LEED v4 BD+C of https://www.leedonline.com/projects.