Forum quick links
SRI Value for concerete
NC-2009 SSc7.2:Heat island effect - roofposted by soha yamani on
Is there a standard SRI Value for concrete that i can use to comply with the credit requirements ? as a part of the roof i am using is concerete and the specs is not addressing this part
Trucks
NC-v4 LTc7:Reduced parking footprintposted by Tarek on
In a warehouse Project, for determining the actual parking capacity of the project, are the Trucks counting in the parking spaces ?
Campus for a gated residential/commercial compound versus ND
posted by ABDELHAMID BESHARA on
We have a gated Residential Compound consisting of around 60 buildings - 4 to 5 stories high - different models.
Cnstrctn began with no LEED intent nw thy wnt rsume seeking LEED
NC-2009 SSp1:Construction activity pollution preventionposted by Aly Adel on
Hello! We have a project that started construction some time ago, and stopped 1 yr ago, leaving only phase 1 (concrete slabs only).
voc for Damp proofing paints under ground
NC-2009 IEQc4.2:Low-emitting materials - paints and coatingsposted by soha yamani on
Hi all , do damp proofing paints that are used to paint concrete foundations, retaining walls, and column necks are considered inside the building ?
Campus approach in a gated residential compound or ND?
posted by ABDELHAMID BESHARA on
We have a gated Residential Compound consisting of around 60 buildings - 4 to 5 stories high - different models.
Separating Pantry Zone
NC-2009 EAp2:Minimum energy performanceposted by Omar Elrawy on
Dear all, I have a case where I need to know if I should model separate Pantry zone in Both Basecase and Proposed Case, or in Basecase only? I have an office building with one System 8
Shipping Room
NC-2009 IEQc6.2:Controllability of systems - thermal comfortposted by Omar Elrawy on
Dear All, We have a shipping room in our office NC building. The room has 11 lockers, each locker has a chair for 1 occupant.
Concerning Signatories
NC-2009 EAc3:Enhanced commissioningposted by Omar Elrawy on
I need to know if the two signatories on the EA CREDIT 3: ENHANCED COMMISSIONING - LEEDOnline form are to be signed by the CxA, or by the owner?
Concerning Underground Basements
NC-2009 SSc6.1:Stormwater design - quantity controlposted by Omar Elrawy on
Dear all, My project is two underground basement parking floors, that are built on the total land area, while the above-grade floors are built on 30% of the total land area. Should I