Forum quick links
Tool for LCA
NC-v4.1 MRc1:Building Life-Cycle Impact Reductionposted by Martin Maribo on
Can the Danish tool, LCAbyg, for MR Credit: Building Life-Cycle Impact Reduction be used for a project in Denmark?
EQp2
EBOM-v4 EQp2:Environmental Tobacco Smoke Controlposted by Alice Andersen on
Hi LEEDuser
I have two questions:
Walkscore only for a few countries?
NC-v4.1 LTc4:Surrounding Density and Diverse Usesposted by Maria Porter on
I investigated the new option 3 for this credit. The only information required is a screenshot of the Walkscore.
Green Cars
EBOM-v4 LTc1:Alternative transportationposted by Alice Andersen on
I am a little unsure about how to manage the question regarding green cars in connection of the evaluation and calculation of green transportation LTc1.
Wood decking on roof
CS-v4 SSc5:Heat island reductionposted by Maria Porter on
Has anybody had success in getting an SRI-value for wood (pine for example or other light wood that turns grey with age)? Saw a discussion about this in the v2009 forum that led to nothing.
Definition of ”Housing” in Diverse Uses
NC-v4 LTc4:Surrounding density and diverse usesposted by Maria Porter on
One use type is “Community anchor uses - Housing (100 or more dwelling units)”.
Glare control requirements for Nordic projects
NC-v4.1 EQc7:Daylightposted by Medina Deliahmedova on
Dear All,
I am an engineer at Inform Design (consulting practice based in Sweden), and we are working on a large office building project which aims to acquire LEED certificate.
Does the paring now have to be on-site?
CS-v4.1 LTc8:Electric Vehiclesposted by Maria Porter on
I have had many projects in v2009 that have had their parking in a neighboring garage if they don’t have their own garage. I have ongoing projects in v4 with the same situation.
EU Special Area of Conservation - ACP?
NC-2009 SSc5.1:Site Development—Protect or Restore Habitatposted by Devyn Olson Sawyer on
Our project is located in the west of Ireland. The project is a warehouse extension (a single LEED project) on an existing commercial campus, and the entire campus is the same owner/occupier.