Option-3: Irrigation Meter Installed

EBOM-v4 WEc1:Outdoor water use reduction
posted by  VISHESH AGARWAL  on 

i am working on the project where project team use the STP Non potable water used for irrigation purpose. so i am reducing the 100% potable water. can i sufficient to achieve this credit.

1
Wed Mar 8, 2017, 11:34 pm

Project located in a building with a very low fresh air rate

Retail-NC-v4 EQp1:Minimum indoor air quality performance
posted by  Valentin Grimaud  on 

What if the project is located inside a 30-year old building with AHU supplying less than 10% fresh air rate? As we have to use the centralized ventilation system and we couldn't make any change t

1
Tue Jan 17, 2017, 9:15 pm

Floor joists part of interior?

NC-2009 IEQc4.4:Low-emitting materials - composite wood and agrifiber products
posted by  John Covello  on 

Hello, Are floor joists considered part of the building interior? So artificial wood used in the joists cannot have urea formaldehyde?

1
Fri Dec 11, 2015, 3:41 pm

Platinum Certification

EBOM-2009 EAp2:Minimum energy efficiency performance
posted by  Muzammal Abbas LEED AP (BD+C)  on 

We had submitted one of our LEED EBOM project final review and received 72 points. We had accepted the review and received Certified Gold Level.

1
Fri Feb 3, 2017, 2:57 pm

Site Management Policy but No Landscaping

EBOM-v4 SSp1:Site management policy
posted by  Nitesh Kumar J  on 

I'm looking for some guidance regarding Site management policy. There is no scope of landscaping or soil in the existing site, then how do we attempt this prerequisite.

1
Fri Mar 24, 2017, 11:00 pm

Modeling OA with Demand control ventilation

CS-2009 EAp2:Minimum energy performance
posted by  Indochine Engineering VN  on 

Hi, I have demand control ventilation for every AHU.

1
Thu Sep 25, 2014, 1:18 pm

Is it too late to do SSp1?

NC-2009 SSp1:Construction activity pollution prevention
posted by  Indochine Engineering VN  on 

Hi, My project is a hotel and client just decided to do LEED when Construction of structure is almost done.

0

Proposed Case-Process Load

NC-v4 EAp2:Minimum energy performance
posted by  Muzammal Abbas LEED AP (BD+C)  on 

Hi, Is there any limitations in LEED V4 regarding process energy that it should be minimum 25% (In proposed case) of the baseline energy cost for the building.

1
Wed May 24, 2017, 4:24 pm

Dormitory as support building

NC-2009 PIf2:Project Summary Details
posted by  ABDUL MUTHALIB MOHAMED  on 

We would like to register a factory building in Bangladesh. Th built up area of factory building is 2 lakh SFT, Ground level only.

1
Fri Apr 29, 2016, 12:24 pm

LIFT Lobbies to be included in VRP Calculations

CI-2009 IEQp1:Minimum indoor air quality performance
posted by  Preethi Ranjith  on 

i want some clarity on whether it is necessary to include Lift lobbies in VRP calculation to demonstrate compliance under IEQp1 and IEQc2? These lift lobbies are not regularly occupied.

0