Spray adhesives has VOC Contents and GREENGURAD certificate also. This material can be use?

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Eunjoo Park  on 

My project located in South Korea. So I often fall into difficulties to interpretation manufacture data.

The material is "Scotch-WeldTM Hi-Strength Postforming 94 CA".

0

About Spray adhesives, Material has voc g/l limit and Greenguard certificate.

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Eunjoo Park  on 

My project is located in South Korea, so I open fall into difficulties to interpret manufacture data. 

0

one product both meet two criteria in option2.

CI-v4 MRc4:Building product disclosure and optimization - sourcing of raw materials
posted by  Renaud Gay  on 

Dear All, for option 2 calculation, I have a question on it. My project is a CI retail project. They will use carpet which include recycled content.

8
Sun Apr 22, 2018, 7:09 pm

What is the base building service water?

CI-v4 EAc3:Advanced energy metering
posted by  JASON NIEN  on 

In the LEED CI V4 standard. Base building service water heating does not need to be metered.So someone can tell me what kind of use belongs to base building service water, thanks advance.

1
Thu Mar 8, 2018, 4:50 pm
2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Wed Feb 21, 2018, 12:24 am

LEED ND v4 MPR2 project area

ND-v4 MPR2:Must use reasonable LEED boundaries
posted by  wenting ding  on 

We are considering applying for a LEED ND cergification.

0

Charging station being networked to encourage off-peak charging

NC-v4 LTc8:Green vehicles
posted by  ERM Korea  on 

Hi. I would like to ask on the requirement of EVSE.

 

1
Tue Feb 13, 2018, 7:20 am

drainage area for sediment basin

NC-2009 SSp1:Construction Activity Pollution Prevention
posted by  Hongyun Zhou  on 

when calculating the volume of sediment basin, what is the drainage area? Should I use footprint of the building or total land area of LEED boundary?

5
Mon Feb 12, 2018, 10:06 am

How to calculate the Tank size

NC-v4 SSc4:Rainwater management
posted by  Patrick Y P Lui  on 

I am working a hotel project with 6090 sq.m greenery + 14210 sq.m pavement and willing to get 3 points by Percentile of rainfall events (Option 1) - Path 2 98th Percentile.

0