Forum quick links
Regularly Occupied Space
EBOM-2009 PIf3:Occupant and Usage Dataposted by Saul Pichardo, AIA on
Hello, Where can I find information on what is considered "regularly occupied space" in a warehouse facility that has most of its space dedicated to product storage and much of the open area used
Subtraction of utility's renewable energy sources from RECs?
NC-2009 EAc6:Green powerposted by Erica Downs on
This may be a silly question, but I said I would ask... If we can document that XX% of our client's utility-provided electricity is from renewable sources (wind, hydro, solar), can they just purch
Partial Purchased Energy
NC-2009 EAp2:Minimum Energy Performanceposted by Christopher Strunk on
Good afternoon. I'm getting started on a model for a county courthouse office expansion. In its pre-renovated state, the facility purchases both HW and CW through the local utility.
FSC Certified Plywood
NC-2009 MRc7:Certified Woodposted by Andy Prestridge on
I have a lot of plywood that is being used on the job that is supposed to be FSC Certified.
Furniture Cost
CI-2009 MRc5:Regional Materialsposted by Morteza Kasmaei on
In a LEED-CI project, can we attempt for MRc4, MRc5, and MRc7 but not included cost of furniture in the calculator? It means that the furniture is not included in any of the LEED-CI credits.
Car Dealership
NC-2009 SSc4.3:Alternative Transportation—Low-Emitting and Fuel-Efficient Vehiclesposted by Robert Shields on
We are working on a project to build a Toyota Dealership in Pennsylvania and the owner is seeking LEED Certification (LEED 2009).
Must I continue to audit if 50% is reached during PP
EBOM-2009 MRc7:Solid Waste Management—Ongoing Consumablesposted by Vanessa Seibert on
Our building did divert 50% of ongoing consumables during out last LEED EBOM certification in 2010. We did perform a waste audit at that time so we acquired MRc6.
C&S Individual Project within a Campus Registration
posted by Nate Steeber on
This may be a very simple question, and perhaps our team is looking into this too deeply: We have a campus which we intend to use a Master Site with individual registrations (i.e. not a group).
Areas passing at one time but not another
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Lisa Fabula on
If part of the building area passes at 9am but does not pass at 3pm does that mean we cant use that 9am area for that time.
Hello,
I am documenting this
NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by Michael Russo on
Hello, I am documenting this credit using the simulation method. For many of the regularly occupied spaces, the rooms are above the 10fc requirement except for a small corner of the room.