Hi,
I previously filed an innovation credit with my design preliminary submission and received an comment from GBCI therefore it is pending. I am getting ready to submit my design final package but want to apply for a different innovation credit and defer it to the construction package. Would it be done ? If so, do I need to mention in my response that I am changing the credit and deferring it to the construction package ?
TODD REED
Energy Program SpecialistPA DMVA
LEEDuser Expert
889 thumbs up
May 22, 2015 - 9:04 am
You can wait to submit a new ID credit in the construction phase. It's best to put a response notifying the review team that this is what you are doing yet is not required.
Matt Dem
3 thumbs up
May 22, 2015 - 9:23 am
Todd,
Thank you very much.