Hydrogen Production

NC-2009 EAc2:On-Site Renewable Energy
posted by  Kristopher Lashley  on 

Hi, We are looking to install an on-site hydrogen production station that will produce hydrogen that is then sent to hydrogen charging stations around the project to refuel and run a fleet of hdrog

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Mar 1, 2016, 4:24 pm

Walking distance from the barracks

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  Jose Dehitta  on 

Our project is a cafeteria which is inside the military base. All the soldiers walks from their barracks to eat or pick up food at the cafeteria. Can we use Option #2 to get 6 points?

3
Mon Feb 29, 2016, 9:48 pm

Concessions Spaces

LEED Reviews: Appeals, Design/Construction Submittals, and more
posted by  Deborah Ebersole  on 

We are looking to certify nineteen concession spaces in an existing airport. The spaces all share one mechanical system and one water source and do not appear to be sub-metered.

2
LEED Fellow
Integrated Design + Energy Advisors, LLC
LEEDuser Expert
377 thumbs up
Sat Feb 27, 2016, 9:11 pm

Providing dedicated area for mercury-containing products?

Healthcare-v2009 MRp2:PBT source reduction - mercury
posted by  Richard Barlow  on 

We are trying to respond to Prelim. Design review comments on a LEED-HC v2009 project for an Inpatient Hospice and Palliative Care facility.

2
Thu Feb 25, 2016, 2:24 pm

Option B for a reception area in a massive office tower lobby

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Elliot Young  on 

So, back again to ask another one. We are ever so close to reaching 75% threshold and without having the engineers run daylight models or measure the space I'm trying to pick up any space we can.

3
Default Avatar
Designer
Rinkachung Architecture
LEEDuser Basic Member
1 thumbs up
Wed Feb 24, 2016, 1:40 pm

Light in open 3 story mezzanines

NC-2009 IEQc8.1:Daylight and Views—Daylight
posted by  Elliot Young  on 

We just received our design credit responses and used method 2 - Prescriptive. We have a 3 story cafeteria space within a 30 story office building.

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Fri Feb 19, 2016, 10:37 pm

School as a Teaching Tool and Green Education

NC-2009 IDc1:Innovation in Design
posted by  emily reese moody  on 

I am posting my question here, since it appears the v2.2 ID forum is closed for new comments. I have a v2.2 LEED-NC Campus project working on the final construction submission.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Thu Feb 18, 2016, 7:50 pm

Existing Building Baseline WWR

NC-2009 EAc1:Optimize Energy Performance
posted by  Christian Kaltreider  on 

Referencing 90.1 Table G3.1.5: I understand that the envelope for an existing building baseline model should reflect existing conditions concerning thermal properties of walls and windows.

4
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Feb 16, 2016, 5:58 pm

Outside Mat

NC-2009 IEQc4.3:Low-Emitting Materials—Flooring Systems
posted by  Waterset CDD  on 

Hello, We have an outside mat that needs to be replaced. It was actually glued down during instillation. I would like to know the following: 1.

2
Representative
Vermont House of Representatives
LEEDuser Expert
7780 thumbs up
Fri Feb 12, 2016, 5:31 pm

Waste Oil Fuel

NC-2009 EAp2:Minimum Energy Performance
posted by  Michael Daly  on 

I am working on a project that has two parts to the building. There is an office component and a shop component. The office is going to be heated and cooled with a VRF system.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Feb 11, 2016, 9:49 pm