Campus District Cooling Tower

NC-v4 WEc3:Cooling tower water use
posted by  Heather Zeto  on 

Our project is on a University campus, which utilizes a Distrcit Plant.  There is no Cooling Tower directly within our project, but there is one at the District Plant.

2
Senior Sustainability Manager
WSP - Built Ecology
LEEDuser Expert
188 thumbs up
Tue Oct 2, 2018, 6:45 pm

Enchanced Cx - District/Campus System Guidance - Floor Area trigger

NC-v4 EAc1:Enhanced commissioning
posted by     on 

One of the triggers of the upstream equipment Cx requirements for EAc1 is that the "project building's gross floor area is greater than 50,000 square feet." Does this 50,000 GSF trigger refer to th

0

Option 4 - whole building life cycle assessment

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Chloe Naese  on 

Hello, could this credit be pursued for a major renovation of a building, or does it only apply to new construction? Thanks!

3
Senior Sustainability Consultant
Steven Winter Associates
LEEDuser Premium Member
9 thumbs up
Tue Oct 2, 2018, 1:11 pm

Shuttle between building and secured site entrances

NC-2009 SSc4.1:Alternative Transportation—Public Transportation Access
posted by  J Douglas Dietrich  on 

Distance from LEED building to public transit stops is too far to meet requirements, however distance from the guardhouse gate controlling access to the secured site on which the LEED building is l

4
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Fri Sep 28, 2018, 10:48 am

SSc6

EBOM-v4 SSc6:Site improvement plan
posted by  Yaretzy Charo  on 

What does it mean by documentation of existing site conditions? 

3
Thu Sep 27, 2018, 9:08 pm

Asphalt with Recycled content (RAP)

NC-2009 MRc4:Recycled Content
posted by  Rick Alfandre  on 

Has anyone used Ashpalt with recycled asphalt?  Reading the forums, it seems it will apply, but I'm having trouble determining what possible percentage of recycled content (pre or post consume

2
Wed Sep 26, 2018, 7:27 pm

Small Project BoD

CI-2009 EAp1:Fundamental Commissioning of Building Energy Systems
posted by  Claire Cowling  on 

I picked up a project in my firm after the first review was compelted. It seems that a BoD was never created for this project, as it is very small and the CxA was hired late.

0

Student Dormitory: Institutional or Residential?

NC-v4 LTc6:Bicycle facilities
posted by  Dan Jaconetti  on 

Can a student dormitory be considered Institutional (Case 1) or does it need to be calculated as Residential (Case 2).  Some people are saying that its housing so it must be residential howeve

2
Sustainable Design Lead
CannonDesign
LEEDuser Expert
379 thumbs up
Mon Sep 24, 2018, 2:17 pm