Clarification Re. General Emissions Requirement for Multi-part Acoustical Wall Treatment

NC-v4 EQc2:Low-emitting materials
posted by  Vanessa Nelson  on 

We have a project with sound recording studios with drywall throughout and an acoustical wall treatment that will be assembled on site and attached to select portions of the drywall.

0

Industry-Wide EPD - error in description?

NC-v4 MRc2:Building product disclosure and optimization - environmental product declarations
posted by  Megan White  on 

Hi all, In the ref guide (p.514), it states that as part of Industry Wide EPD "the manufacturer is explicitly recognized as a participant by the program operator." However, this is the same exact

4
Mon Mar 9, 2020, 3:37 pm

v2009 - SSc1: Site Selection - Wetland Protection

NC-2009 SSc1:Site selection
posted by  Kathy Hrabovsky  on 

Is a Category 1 Forest Conservation Easement permitted to protect the limits of disturbance between a project site and an existing wetland if the project site is 60', instead of 100', from a wetlan

0

Uplight - lumens emitted above horizontal

NC-v4 SSc6:Light pollution reduction
posted by  Amanda Cunningham  on 

Can anyone clarify if the maximum allowed percentage of total lumens emitted above horizontal (by lighting zone) is applied to each individual luminaire or the sum of all lumens from all luminaires

3
Wed Mar 4, 2020, 7:40 pm

Where to look for manufacturer documentation

NC-v4 EQc2:Low-emitting materials
posted by  Lissa Spitz  on 

Is it just me?  I'm having a hard time finding manufacturer documentation that confirms compliance with CDPH, aqBB, etc.

9
Wed Mar 4, 2020, 4:29 pm

LEED v4.1 Renewable Energy Production

NC-v4.1 EAc5:Renewable Energy
posted by  Ruju Rathod  on 

We are evaluating the possibility of applying for the Renewable Energy Production credit under LEEDv4.1 for an office building that is receiving renewable energy from the grid.

3
Default Avatar
Sr. Sustainable Design Specialist
HOK
LEEDuser Basic Member
1 thumbs up
Tue Mar 3, 2020, 11:13 pm
1
Tue Mar 3, 2020, 10:14 pm

Long Term Bike Storage - Distance to Building Entry

NC-v4 LTc6:Bicycle facilities
posted by  Catherine Blakemore  on 

I this question on the v4.1 forum, but have received an answer and am hoping for better results on the v4.0 forum.

 

1
Tue Mar 10, 2020, 3:33 pm

75% compliance within office no longer allows us to count all SF?

NC-v4 EQc8:Quality views
posted by  emily reese moody  on 

In v3, if 75% of an office complied, we were allowed to include the whole SF of that space in our calcs.

2
Sustainable Design Leader
HKS, Inc.
LEEDuser Premium Member
40 thumbs up