EBOM-2009 MRc6:Solid waste management - waste stream auditposted by Emmanuel Pauwels on
We are doing a waste audit and we evaluate metals, mixed paper, cardboard, glass, plastics, batteries, and fluorescent lamps.
PIf2 form filling
CI-2009 MPR7:Must comply with a minimum building area to site area ratioposted by Lorenna Lobo on
While filling the PIf2 form, in "site characteristics" it asks what is the total site area within the LEED project boundary, but the project is just a tenant space, should I put 0?
WEp1 calculator
NC-2009 WEp1:Water use reductionposted by Muriel Alvarez on
Dear Since I have a problem with BETA version for WEp1, the form did not calculated the percentage correctly, I´ve decided to use the v06 form calculator, well...
DCV vs IEQp1
NC-2009 IEQp1:Minimum indoor air quality performanceposted by Marina Andrade on
Hi everyone! I have a project that the system works with outside air demand according to the CO2 sensor.
Views
NC-2009 IEQc8.2:Daylight and views - viewsposted by Antonio Macedo Filho on
I would like to know if there is a maximum obstruction height of views for option 1.
Sediment trap outside the project boundary
NC-2009 SSp1:Construction activity pollution preventionposted by Gabriela Mesquita on
It plans to build a building in a very broad field of the same owner. The LEED Boundary was defined based on the area that is planned to disrupt.
PI Form 2: MPR7
CI-2009 MPR7:Must comply with a minimum building area to site area ratioposted by Aline Luther on
For a project of a commercial interior (commercial office in a commercial building) the gross floor area correspond to the total area of the office?
Pressure Drop Adjustment
NC-2009 EAp2:Minimum energy performanceposted by Marina Andrade on
How do I set which the fan power limitation adjutment pressure drop I use at baseline? The standard display multiple values for MERV filters, exhaust and others. What should I use at baseline?
Certifying an addition to an existing building with LEED NC
NC-2009 PIf1:Minimum Program Requirementsposted by Veronica Reed on
Hello, we are working on a project, an addition to an existing building and we would like to certify but don't know if LEED NC would apply.
Scope in a C&S shopping mall
CS-2009 EAp2:Minimum energy performanceposted by Alan Viale on
We are working on a new shopping mall. as usually in my country, a anchor store (tenant deparment store) was first developed and constructed, and now is operating.