cardboard and paper

EBOM-2009 MRc6:Solid waste management - waste stream audit
posted by  Emmanuel Pauwels  on 

We are doing a waste audit and we evaluate metals, mixed paper, cardboard, glass, plastics, batteries, and fluorescent lamps.

1
Thu Jul 23, 2015, 5:14 pm

PIf2 form filling

CI-2009 MPR7:Must comply with a minimum building area to site area ratio
posted by  Lorenna Lobo  on 

While filling the PIf2 form, in "site characteristics" it asks what is the total site area within the LEED project boundary, but the project is just a tenant space, should I put 0?

0

WEp1 calculator

NC-2009 WEp1:Water use reduction
posted by  Muriel Alvarez  on 

Dear Since I have a problem with BETA version for WEp1, the form did not calculated the percentage correctly, I´ve decided to use the v06 form calculator, well...

0

DCV vs IEQp1

NC-2009 IEQp1:Minimum indoor air quality performance
posted by  Marina Andrade  on 

Hi everyone! I have a project that the system works with outside air demand according to the CO2 sensor.

1
Wed Oct 29, 2014, 4:59 pm

Views

NC-2009 IEQc8.2:Daylight and views - views
posted by  Antonio Macedo Filho  on 

I would like to know if there is a maximum obstruction height of views for option 1.

1
Thu Aug 17, 2017, 1:29 pm

Sediment trap outside the project boundary

NC-2009 SSp1:Construction activity pollution prevention
posted by  Gabriela Mesquita  on 

It plans to build a building in a very broad field of the same owner. The LEED Boundary was defined based on the area that is planned to disrupt.

0

PI Form 2: MPR7

CI-2009 MPR7:Must comply with a minimum building area to site area ratio
posted by  Aline Luther  on 

For a project of a commercial interior (commercial office in a commercial building) the gross floor area correspond to the total area of the office?

0

Pressure Drop Adjustment

NC-2009 EAp2:Minimum energy performance
posted by  Marina Andrade  on 

How do I set which the fan power limitation adjutment pressure drop I use at baseline? The standard display multiple values for MERV filters, exhaust and others. What should I use at baseline?

1
Wed Oct 22, 2014, 3:13 pm

Certifying an addition to an existing building with LEED NC

NC-2009 PIf1:Minimum Program Requirements
posted by  Veronica Reed  on 

Hello, we are working on a project, an addition to an existing building and we would like to certify but don't know if LEED NC would apply.

1
Mon Jan 19, 2015, 7:16 pm

Scope in a C&S shopping mall

CS-2009 EAp2:Minimum energy performance
posted by  Alan Viale  on 

We are working on a new shopping mall. as usually in my country, a anchor store (tenant deparment store) was first developed and constructed, and now is operating.

1
Fri Jun 19, 2015, 4:58 pm