Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

LEED v4 Waste Monitoring unit of measurement in Truck Load

CS-v4 MRc5:Construction and demolition waste management
posted by  Ronnel Flores  on 

Our project's waste quantity was recorded in truck load not in kilograms. This counts as volume?

4
Managing Partner
Innovative Workshop Consulting
LEEDuser Expert
22 thumbs up
Thu Jul 20, 2023, 3:19 pm

Waste Manangement

Warehouses-NC-v4.1 MRc5:Construction and Demolition Waste Management
posted by  Joseph Snider  on 

Working on warehouses in areas that do not have many options for recycling.  Just to be clear, can you do just the waste reduction option of <10 lbs/SF and if so, that is all you put in the

0
2
Thu Jul 20, 2023, 12:36 am

Changing structural systems between the baseline and proposed design

NC-v4 MRc1:Building life-cycle impact reduction
posted by  Ahmed Abd El Fattah  on 

Hello

Is changing from concrete structure to steel structure accepted in LCA?

3
Wed Jul 19, 2023, 4:34 am

Education Programs required to be about the LEED building

NC-2009 IDc1:Innovation in Design
posted by  Lawrence Lile  on 

You can have a wonderful environmental education program, but if it doesn't talk about the LEED building, it will get rejected.

3
Executive Director
Built Environment Plus
LEEDuser Basic Member
9 thumbs up
Wed Jul 19, 2023, 1:29 am

Can ground level landscape be classified as Nonroof Measures?

NC-v4.1 SSc5:Heat Island Reduction
posted by  Antonio Poblete  on 

Do areas with ground level landscape count towards any of the calculations? 

1
Wed Oct 4, 2023, 12:41 am

MRc2 BPDO EPD Option 2 Multi Attribute Optimization

NC-v4.1 MRc2:Environmental Product Declarations
posted by  Sarah Linke  on 

Has anyone had success pursuing credit for the BPDO EPD Option 2 (Multi Attribute Optimization)? The companies I have had success finding documentation for are as follows: 

26
Managing Partner
Ecoimpact Consulting
LEEDuser Expert
171 thumbs up
Tue Jul 18, 2023, 5:20 pm

Ventilation in corridors

NC-v4 EQp1:Minimum indoor air quality performance
posted by  Luana Jerez  on 

We are working on an office building 17 meters wide, on one floor, the layout is a 3.5-meter distribution corridor, serving as a division between two rows of offices.

0