List of meters

NC-v4 EAc3:Advanced energy metering
posted by  Vasileios Kalfountzos  on 

Hello all, our project is a Data Center that every single part of it will be metered. Each rack will have two meters while also every electrical panel will have each own meter.

1
Thu Aug 10, 2017, 4:04 pm

Double- Counting of Renewable Energy

CI-v4 EAc4:Renewable energy production
posted by  Bharath Ravuru  on 

Hi, We are going with solar panels on site at our facility. Can I use the renewable energy generated for both on-site renewable energy production credit and also energy savings in the simulation?

1
Mon Aug 28, 2017, 2:09 pm

Phased Flush Out

Schools-NC-v4 EQc4:Indoor air quality assessment
posted by  Cynthia Kaplan  on 

We have a phased reno/add school project that would prefer to earn IEQ 4 by way of post occupancy flush out.

1
Mon Aug 28, 2017, 2:09 pm

Final Cleaning

NC-2009 IEQc3.1:Construction IAQ management plan - during construction
posted by  Benjamin McGrath  on 

For the final cleaning bid package, in our specifications, there is no language requiring that the chemicals used have to be low VOC.

1
Sat Aug 26, 2017, 8:50 pm
1
Sun Aug 27, 2017, 12:07 am

LED integrated in facade window frame/ MLO lighting zone

NC-v4 SSc6:Light pollution reduction
posted by  Ilse Dijkstra-Nugteren  on 

We are working on the LEED V4 certification of a project which will be located at the border of a business park and about 3 kilometers away from highways and an international airport.

1
Fri Aug 11, 2017, 12:33 pm

Vulnerable Populations

NC-v4 SSc1: Site assessment
posted by  Saxon Gibbs  on 

How does LEED define vulnerable populations and what is the best way to assess proximity to them?

1
Mon Aug 28, 2017, 6:45 pm

Building Footprint

CS-2009 SSc7.2:Heat island effect - roof
posted by  Jaesik Lim  on 

Hi, all Our team had a technical advice from USGBC reviewer, the comment is like below... " The LEED form indicates a total roof area (excluding mechanical equipment, photovoltaic panels, and skyl

1
Mon Aug 14, 2017, 6:28 pm

Rainwater Harvesting - Irrigation and Reclaimed Water?

EBOM-v4 WEc4:Water metering
posted by  ARDOR GREEN  on 

We have an office project that will have some large rainwater collection tanks that will be used for irrigation.

1
Mon Aug 28, 2017, 11:25 pm

Registering an individual project under a Campus project

LEED Guidance for Campuses and Multiple Buildings
posted by  Sean Quinn  on 

Does anyone know if we can register an individual project under a master site with only the master site name and ID information and without actually having access to the master site project on LEED

1
Mon Aug 14, 2017, 5:55 pm