Hello all,

our project is a Data Center that every single part of it will be metered. Each rack will have two meters while also every electrical panel will have each own meter. If we add up all of the meters the yielded sum equals to roughly 1,600 meters for the whole building. Nonetheless, the Data Rooms are being repeated which means that Data Room 3 will have the same number of meters as Data Room 1. Should we still mention all of the meters?