Building Envelope Compliance

CI-2009 EAp2:Minimum Energy Performance
posted by  Omar Delgado  on 

Greetings, We're doing a CI project where the glazing far surpasses the 40% wall area allowed on the north wall. However, the envelope will not be altered for this project.

3
President
REAL Building Consultants
LEEDuser Premium Member
27 thumbs up
Thu Mar 8, 2012, 6:33 pm

Entry Way Systems: Floor mats

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Elle Brown  on 

I am working on a government project and half of our building is a garage space. 1. Do we have to put 10 ft long floor mats at each exterior door to the garage?

2
Sustainability Specialist
Wight and Company
LEEDuser Basic Member
415 thumbs up
Thu Mar 8, 2012, 2:42 pm

manufacturing plant: group certification or single structure?

LEED Guidance for Campuses and Multiple Buildings
posted by  Jutta Berns  on 

i probably know the answer already, but i just want to test my understanding: we are in the process of registering a manufacturing plant (BD+C), which consists of an office building and a manufac

2
Sustainability Specialist
Wight and Company
LEEDuser Basic Member
415 thumbs up
Thu Mar 8, 2012, 5:55 am

Energy Star Equipment and Timing

CI-2009 EAp2:Minimum Energy Performance
posted by  Curt Pascoe  on 

I'm bringing up a topic discussed but not solved in previous comments. What does the USGBC include in "equipment installed as part of the tenant's scope of work"?

5
Thu Mar 8, 2012, 4:09 am

Defer Credits

General forums
posted by  Emily Catacchio  on 

Dana,

I recently recieved this response from GBCI:

2
Default Avatar
Architectural Project Coordinator
Crabtree, Rohrbaugh & Associates
LEEDuser Basic Member
1 thumbs up
Thu Mar 8, 2012, 3:49 am

Defining usage groups for tenant scope fixtures.

CS-2009 WEp1:Water Use Reduction
posted by  Luis Miguel Diazgranados  on 

Hi everyone, I'm working on an office building in which efficient bathrooms will be installed as part of the Core and Shell scope.

2
Architect / LEED AP BD+C
KILTIK Consultoría
LEEDuser Basic Member
36 thumbs up
Wed Mar 7, 2012, 5:50 pm

ASHRAE 90.1 2007 Humidification system

NC-2009 EAc1:Optimize Energy Performance
posted by  Ricardo Marques  on 

Hi! In Ashrae 90.1 2007 appendix G, in baseline simulation, what is the system type for humidification? (If the proposed building has humidification) Many thanks Ricardo

9
Wed Mar 7, 2012, 5:12 pm

Kitchen Hood Exhaust and Make-up Air

NC-2009 EAc1:Optimize Energy Performance
posted by  Cory Duggin  on 

What is the correct way to account for kitchen hood exhaust and the consequential 100% OA makeup energy? This is a commercial kitchen and serving area in a hospital. Thanks in advance.

3
Senior Energy Wizard
TLC Engineering Solutions
LEEDuser Premium Member
44 thumbs up
Wed Mar 7, 2012, 4:28 pm

Fan Power Calculation

NC-2009 EAc1:Optimize Energy Performance
posted by  Smart Green  on 

In base case, how to calculate bhp/cfm value for AHUs if we know flow (in CFM) & cooling capacity (btu/h) details?

5
Wed Mar 7, 2012, 4:14 pm

How much is the allowance for non-flat?

CS-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Gabriela Hernández Castillo  on 

GS-11 on page 13 says that for non-flat topcoat the v.o.c. limit is 100. Is is 100 or 150 (please take a look at the bird's eye view)?

5
Tue Mar 6, 2012, 4:51 pm