Forum quick links
How to calculate the impact of a heat pump, only used for heatin
NC-2009 EAc4:Enhanced Refrigerant Managementposted by Lise Dannesboe on
Hi! We use a heatpump system, which is used to supply heat as back-up solution.
LEED v3 CS Warehouse - MPR Minimum Occupancy Compliance
CS-2009 MPR5:Must comply with minimum occupancy ratesposted by SIG - Sustainability Main Account on
Has there been any previous experience submitting a LEED CS project under v3 with an empty warehouse design, not outfitted with an office and/or restroom to accommodate a FTE?
Hi all,
NC-2009 EAp2:Minimum Energy Performanceposted by Visu Boj on
I am working on a certification for a factory having less than 5 percent conditioned area. My process load is also high upto 75 percent.
Permanent Irrigation System, Temporary Use of Potable Water
NC-2009 WEc1:Water Efficient Landscapingposted by Daniel Costantino on
Hello, I am working on a project where there will be a permanent irrigation system.
Open Floor Plan with different Tvis Values
NC-2009 IEQc8.1:Daylight and Views—Daylightposted by Marisa Britton on
Can I do prescriptive method of calculation for an open floor plan if the N+W glazing walls of the building have a Tvis of 38% and the South + East glazing walls have a Tvis of 56%?
Future Expansion
NC-2009 SSc5.2:Site Development—Maximize Open Spaceposted by Karl Heitman on
Our project, an industrial manufacturing facility, is expecting future expansion, and it has been noted on our permit/construction drawings.
VERTICALLY ATTACHED BUILDINGS
posted by Vincent Dupuy on
Hello, I work on a building which contains 2 sections and only one of them would like to go with LEED EBOM. The first section (which wants leed certification) is principally offices.
What is the acceptable testing standard for runoff coefficient.
NC-2009 SSc6.1:Stormwater Design—Quantity Controlposted by Panupant Phapant on
Dear All We are the construction materials manufacturers.
Does CI fit into BD+C?
posted by Sara Greenwood on
Hello, I am developing TI Guidelines for unfinished retail space in a building pursuing BD+Cv2009. Can the future tenant pursue CI?
ASHRAE standard
NC-2009 EAp2:Minimum Energy Performanceposted by Nelina Loiselle on
Hello, Can someone let me know if ASHRAE 90.1 2010 is acceptable to use in relation to lighting or is 90.1 - 2007 still required to be used?