Post a question or comment
Filter by location
Forum
Topic
Replies
Recent

Credit Wording

CI-2009 WEc1:Water Use Reduction
posted by  Matthew Fortin  on 

I am in the process of certifying a CI space.

5
Wed Nov 9, 2016, 3:35 pm

Fan Power and Fan Power Adjustment (FPA)

NC-2009 EAp2:Minimum Energy Performance
posted by  Vassil Vassilev  on 

Greetings, In the project we are modeling, the following issues are still not quite clear for us and we'd appreciate any advice on the matter. Baseline system is 8.

6
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Tue Nov 8, 2016, 3:48 pm

Future Alternative Compliance Paths

Pilot-Credits PC14:Walkable Streets
posted by  Douglas Flandro  on 

I would like to see some more options added to this credit to encourage walking on the project site such as tables and benches with solar powered charging stations, outdoor theaters, performance ar

2
Default Avatar
LPAS Architecture + Design
LEEDuser Basic Member
0 thumbs up
Tue Nov 8, 2016, 1:37 pm

NFRC Rated Fenestration

NC-2009 EAp2:Minimum Energy Performance
posted by  Jatuwat Varodompun  on 

For the proposed model, can we refer to table A8.2 for U-factor of the window but refer SHGC and VLT to the manufacturing data (tested based with NFRC standard)?

7
Mon Nov 7, 2016, 3:50 pm

Process - Transport Refinery Energy

NC-v4 EAc2:Optimize energy performance
posted by  Victoria Watson  on 

Hi, Is there any precedent for being able to exclude fuel refinery energy from an energy model.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Sun Nov 6, 2016, 2:24 am

Through Connections

ND-v4 NPDc6:Connected circulation network
posted by  Martine Desbois  on 

Hello Elliot, Following up on the last question, the reference guide refers to pedestrian and bicycle connection for culs-de-sac. From your response I assume it applies to all through connections.

4
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Fri Nov 4, 2016, 5:48 pm

C&D Waste Recycling Calculations for 200 yr-old bldg renovation

NC-2009 MRc2:Construction Waste Management
posted by  Debra a. Lombard  on 

C&D Waste Recycling Calculations for 200 yr-old bldg renovation: This 200 yr-old brick building had a tremendous amount of old brick that was falling apart and needed to be taken out and re-po

2
Default Avatar
LEEDuser Expert
472 thumbs up
Fri Nov 4, 2016, 5:07 pm

requirements for secure bicycle storage?

NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Rooms
posted by  Erin Holdenried  on 

Are racks or bike stands needed? I have a project with a designated area for bicycle storage.

2
Senior Principal | Director of Sustainability Integration
SmithGroup
LEEDuser Expert
43 thumbs up
Fri Nov 4, 2016, 3:43 pm

Included wooded area in LEED boundary?

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Erica Downs  on 

The project is on a college campus, and the site itself if previously developed.

3
Default Avatar
LEED Consultant
The Green Engineer
LEEDuser Basic Member
188 thumbs up
Thu Nov 3, 2016, 9:11 pm

exemplary performance

ND-v4 INc1:Innovation
posted by  Ian Scott  on 

I purchased my v4 reference guide last year and the listing of exemplary performance options differs in the table 5: Scorecard and policy areas and the information listed under each credit.

2
LEED AP-ND, Principal
Criterion Planners
LEEDuser Expert
231 thumbs up
Wed Nov 2, 2016, 9:27 pm