Residential Switched Receptacles

NC-2009 IEQc6.1:Controllability of Systems—Lighting
posted by  Alexis Thompson  on 

To satisfy credit requirements should we provide the corresponding light fixtures for switched receptacles in residential units in a multi-family high-rise project?

4
Sustainability Specialist
Sellen Sustainability
LEEDuser Basic Member
8 thumbs up
Wed Nov 16, 2016, 1:17 am

On-site waste water treatment

NC-v4 WEc2:Indoor water use reduction
posted by  Lorne Mlotek  on 

In LEED 2009 there was a credit dedicated for reducing waste water or treating it on site. How does LEED V4 reward onsite treatment?

3
BASc., LEED AP BD+C, O+M
LeadingGREEN Training and Consulting Inc, Viridis EC LLC
LEEDuser Basic Member
20 thumbs up
Mon Nov 14, 2016, 6:37 pm

Achieving Innovation Design: MRc2 (95%)

NC-2009 MRc2:Construction Waste Management
posted by  James Goldfield  on 

Hello Everyone, I am currently on a project where one of our goals is to achieve Innovation Design: MRc2 Exemplary Performance (95%).

3
Default Avatar
LEEDuser Expert
472 thumbs up
Mon Nov 14, 2016, 5:10 pm

CWM Campus Credit

NC-2009 MRc2:Construction Waste Management
posted by  ethen mcmanus  on 

My project is composed of 10 buildings on a college campus. I know for a fact the CWM credit is a campus credit. How do I document this? Do i go to each building on LEEDONLINE and upload?

2
Sun Nov 13, 2016, 8:34 pm

Multiple Street Frontages

Pilot-Credits PC14:Walkable Streets
posted by  Carrie Webster  on 

Our project is on a corner and has two street frontages, with the primary façade on the "main street" and one side along a side street.

2
Default Avatar
Designer
Glave and Holmes Architecture
LEEDuser Basic Member
0 thumbs up
Sun Nov 13, 2016, 12:15 am

Energy Recovery Bypass

NC-2009 EAp2:Minimum Energy Performance
posted by  Kalyan Nishtala  on 

Hi, I am working on a building which includes DOAS units with energy recovery cores on the proposed systems. The baseline systems do not require energy recovery per ASHRAE 90.1-2007.

2
Senior Energy Wizard
TLC Engineering Solutions
LEEDuser Premium Member
44 thumbs up
Fri Nov 11, 2016, 5:09 pm

RWH Pond outside LEED Boundary

NC-2009 PIf4:Schedule and Overview Documents
posted by  ABDUL MUTHALIB MOHAMED  on 

Our project building is located in a campus and it is registered individually. Rainwater harvesting pond is located in the campus but it is outside the LEED Boundary.

3
LEED Fellow, WELL AP
JLL
LEEDuser Basic Member
125 thumbs up
Fri Nov 11, 2016, 4:42 am

Building Envelope Cx Checklist for LEED Documentation

NC-v4 EAc1:Enhanced commissioning
posted by  Joyce Kelly  on 

I am currently developing a Building Envelope Cx Checklist for LEED v3 projects.

8
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Nov 10, 2016, 2:49 pm

OPTION 2. ENVELOPE COMMISSIONING (2 POINTS)

NC-v4 EAc1:Enhanced commissioning
posted by  Ciaran McCabe  on 

Can anyone identify the range of Building Envelope seasonal tests that are required to satisfy Option 2. Is there a typical list of activities outlined by LEED.

2
LEED Fellow
7group / Energy Opportunities
LEEDuser Expert
4454 thumbs up
Thu Nov 10, 2016, 2:40 pm

2009 NC form for substitution

NC-2009 IEQc4.1:Low-Emitting Materials—Adhesives and Sealants
posted by  Yukari Treible  on 

Trying to substitute the NC 2009 IEQc4 forms in place of 2009 Schools, but can't find a valid form download. Anything I find says it's a reference only sample form.

5
Construction Administrator/ LEED AP
Bywater Woodworks, Inc.
LEEDuser Basic Member
42 thumbs up