Cork Bulletin Boards and Marker Boards

NC-2009 IEQc4.4:Low-Emitting Materials—Composite Wood and Agrifiber Products
posted by  Abena Darden  on 

Does anyone know if cork bulletin boards or marker boards typically have urea formaldehyde resins?

2
Technical Information & Public Affairs Manager
UL Environment
LEEDuser Basic Member
356 thumbs up
Thu Apr 5, 2012, 6:02 pm

Achieving IEQc1 with no ventilation as part of C&S project

CS-2009 IEQc1:Outdoor Air Delivery Monitoring
posted by  Tony Schafer  on 

Can this credit be achieved if there will be no ventilation as part of the C&S project?

3
Thu Apr 5, 2012, 5:45 pm

Relocating Furniture

CI-2009 MRc5:Regional Materials
posted by  Sheela I  on 

Hello, I am working on a LEED CI project and we are reusing most of the furniture at the new office location. The distance between new and the previous office is with in 500 miles.

3
Thu Apr 5, 2012, 2:41 pm

Negative Pressure Differential Requirement

NC-2009 IEQc5:Indoor Chemical and Pollutant Source Control
posted by  Maya Karkour  on 

Dear all, One of the credit requirements is that: "The pressure differential with the surrounding spaces must be at least 5 Pa on average and 1 Pa at a minimum when the doors to the rooms are clos

2
Director of Intersectional Professional Services
LEEDuser Basic Member
41 thumbs up
Wed Apr 4, 2012, 8:23 pm
5
Wed Apr 4, 2012, 6:06 pm

Does a crisis center require covered storage for bikes?

NC-2009 SSc4.2:Alternative Transportation—Bicycle Storage and Changing Rooms
posted by  Megan Dougherty  on 

Our project is a crisis center which provides drop-in services and short term residential services. The drop in portion is considered an institutional project.

2
Default Avatar
Sustainability Coordinator
Dougherty + Dougherty Architects
LEEDuser Basic Member
1 thumbs up
Wed Apr 4, 2012, 5:46 pm

Site disturbance from a project surrounded on all four sides

NC-2009 SSc5.1:Site Development—Protect or Restore Habitat
posted by  Achelles DSouza  on 

I am working on a project which is surrounded by existing facilities on three sides, and road on the fourth side.

3
Default Avatar
Sustainability Engineer
Freelance Building Simulator
LEEDuser Basic Member
7 thumbs up
Wed Apr 4, 2012, 5:38 pm

Views and window coverings

CI-2009 IEQc8.2:Daylight and Views—Views for Seated Spaces
posted by  Nancy Goshow  on 

Can you still achieve the views credit if you have a commercial interiors space meeting all of the requirements of the credit except that due to security purposes the horizontal blinds need to be

2
Energy Program Specialist
PA DMVA
LEEDuser Expert
626 thumbs up
Wed Apr 4, 2012, 2:52 pm

Underground Parking and IEQ 4

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Ibrahim El-Shair  on 

What are possible conditions to enable excluding underground parking from calculations of IEQ 4 - Low emmiting materials? if we have 3 underground levels of parking and they have the following con

5
LEED Construction Coordinator, Sustainability Professional
DAR
LEEDuser Basic Member
4 thumbs up
Tue Apr 3, 2012, 4:23 pm

Paint on the inside of pipes

NC-2009 IEQc4.2:Low-Emitting Materials—Paints and Coatings
posted by  Emmanuel Pauwels  on 

Our project has a district heating and cooling system. The inside of the pipes that connect the building with the district heating and cooling system have a paint.

2
LEED Construction Coordinator, Sustainability Professional
DAR
LEEDuser Basic Member
4 thumbs up
Tue Apr 3, 2012, 4:17 pm