Forum quick links
Legal Wood ACP calculator -
Pilot-Credits MRpc102:Legal Woodposted by Arwid Theuer-Kock on
We are forced to use the v4_v2009_Legal Wood ACP calculator_v02_0 calculator.
former we could enter the product price and the percentage of new wood certified.
Battery room (Litium-ion)
Data-Centers-NC-v4 EQc1:Enhanced indoor air quality strategiesposted by Suksan Yongwattananun on
Our data center project has had litium-ion battery rooms which the pollution from battery can't occur in normal operation because of the litium-ion battery type.
ventilation in Walk-in Coolers
Warehouses-NC-v4 EQp1:Minimum indoor air quality performanceposted by Francesco Passerini on
Hello, is ventilation in Walk-in Cooler necessary for the prerequisite? Does the request depend on the indoor setpoint temperature?
Innovation: Occupant comfort survey - Conducting Survey?
CS-v4 INc1:Innovationposted by Instra Ingenieros on
Hi all,
We are developing a Core and Shell certification and we pursue the innovation credit "Occupant comfort survey". The innovation credit requirements tell:
Performing Commissioning Activities 3 years after occupancy
NC-2009 EAp1:Fundamental Commissioning of Building Energy Systemsposted by Gaston Viau on
Hi!
Our NC-2009 project it's a 16,000sqf office building located in California.
Compliant exterior products
Pilot-Credits SSpc154:Heat Island Mitigation with Cool Wallsposted by Michelle Rosenberger on
The Cool Walls database of compliant products does not include a wide range of products. Our warehouse project couldn't find an exterior paint that had elastomeric properties in the database.
Infiltrations
NC-v4 EQp1:Minimum indoor air quality performanceposted by Juan Perez on
Is it feasible to add an infiltration rate into the outdoor air provide per the HVAC to meet the minimum requirement?
No irrigation system- Rainwater
NC-v4 WEc1:Outdoor water use reductionposted by Santiago Avila on
Hello everyone
Currently I am working in a project which does not have an irrigation system, and will be watered with collected water from rainfall.
lighting controls
Retail-CI-v2009 EAc1.2:Optimize energy performance - lighting controlsposted by ARGIA ARROYO BUGANZA on
LEED REQUIREMENT: Verify 15’ perimeter needs to be covered for daylight dimming- This includes private offices-all spaces within 15’ of perimeter- WHAT HAPPENS ONE OF MY FIXTURES (OPEN SPACE)
Opt 2, path 4 Reuse and Salvaged Material requirement
NC-v4.1 MRc1:Building Life-Cycle Impact Reductionposted by Dave Hubka on
I can't seem to find a minimum threshold for the amount of reused / salvaged materials required to be able to achieve all (4) points within Opt 2 Path 4.